  1. Yup, decided to change as due to the beam which separate the store and mbr. Cause above bed can't havbe beam, so need to do false ceiling, which will make the ceiling very "short". Hmmm... for ur planning, what else is missing? Most have settle already right?
  2. Change in Kitchen entrance Common toilet shower area
  3. Updates Separation wall in master bedroom toilet Going to be wardrobe area (Combine store room into master bedroom)
  4. Haha, thanks! So far so good for everything. How's your big planning coming up?
  5. Haha, actually the windows are dark grey, not sure why it turn out green in the photo.
  6. Close Up on Master Bedroom Toilet: Living Room Floor Tiles:
  7. Tiling Process: Start Date: 18/11/09 End Date: Still in progress Experience: Good so far Comment: Tilers are very experience, tiling progress is rather fast, no hiccups so far. Kitchen Tiling: Master Bedroom Toilet: Tiling:
  8. Hmmm, will take noted of the details, thanks for the advice! *Praying for a smooth renovation process too, so far so good, hope it continue. Thanks ya!
  9. Installation of Windows: Start Date: 18/11/09 End Date: 18/11/09 Experience: Good Comment: Window installation was done up pretty nicely, the windows were aligned straight to the walls, resting well without any gaps.
  10. Have not purchase any furniture yet as we have are waiting for the renovation to complete first.
  11. We change the entrance of bedroom 2 and 3 to accommodate a bigger master bedroom cum study room: A view of the living room during the process:
  12. We change the entrance of common toilet: Base for kitchen was build at the same time:
×