Just bought a 5 rooms flat and need some advice on renovation. Is the prize in the quotation reasonable and if there anything that are not necessary to be done as for now?

A KITCHEN ( tiles range from $ 2.5 to $ 3 per sqft )

1 to hack away existing wall tiles , floor tiles , cabinet etc and clear debris off site 1000.00

2 supply and lay ceramic wall ties up to ceiling height 2150.00

3 supply and lay ceramic floor tile with HDB required prepack cement and water proofing

membrane to floor trap area 1200.00

4 to construct a 50mm height kitchen cabinet base and a washing machine base 250.00

5 to fabricate top and bottom kitchen cabinet ( L shape ) with Laminated finishing and

ABS trimming ( approx 57 ft ) 5700.00

6 supply and install solid surface work top ( approx 28ft ) 1820.00

7 supply and install a stainless steel refuse chute 120.00

8 supply and install Aluminum casement window ( silver frame ) with light tinted glass 330.00

9 supply and install a 6 hook aluminum bamboo holder 30.00

10 supply and install a top track frame less Temper glass door at kitchen entrance 600.00

11 supply and install a dish drying rack with a lift up glass door with wooden frame F O C

12 supply labour to install sink , cooker hood , stove and oven F O C

B BALCONY ( tiles range from $ 2.5 to $ 3 per sqft )

1 to hack away existing aluminum sliding door and floor tile and clear debris off site 200.00

2 to raise up balcony flooring with extruded polystyrene foam and Brc mesh 200.00

3 supply and lay 60 cm x 60 cm Homogenous floor tile with skirting 540.00

4 supply and install Aluminum casement window ( silver frame ) with light tinted glass 870.00

5 to apply a layer of cement strengthener to form key on existing wall tiles & provide

Skim coat over it F O C

C COMMON TOILET ( tiles range from $ 2.5 to $ 3 per sqft )

1 to hack away existing wall tiles , floor tiles , toilet bowl and basin and clear debris off site 600.00

2 supply and lay ceramic wall ties up to ceiling height 1650.00

3 supply and lay ceramic floor tiles 500.00

4 supply labour , tool and material to provide water proofing membrane 250.00

5 labour charge to install a toilet bowl 90.00

6 labour charge to install a wash hand basin and tap 80.00

7 supply and install a aluminum frame bi -fold door with Acrylic panel 200.00

8 supply labor to install a storage tank heater 100.00

9 supply labour to install a rain shower ( expose piping / exposed rain shower ) F O C

10 supply and install a frame less tempered glass shower screen with handle 580.00

11 to reposition existing toilet entrance 320.00

12 to fabricate a storage cabinet with laminated finishing 300.00

D MASTER BEDROOM TOILET ( tiles range from $ 2.5 to $ 3 per sqft )

1 to hack away existing wall tiles , floor tiles , toilet bowl and basin and clear debris off site 600.00

2 supply and lay ceramic wall ties up to ceiling height 1650.00

3 supply and lay ceramic floor tiles 500.00

4 to fabricate a storage cabinet with laminated finishing 300.00

5 supply labour , tool and material to provide water proofing membrane 250.00

6 labour charge to install a toilet bowl 90.00

7 labour charge to install a wash hand basin and tap 80.00

8 supply and install a aluminum frame bi -fold door with Acrylic panel 200.00

9 supply and install a long bath with a curb to conceal inlet with tiles finishing 1200.00

10supply and install aluminium frame ( acrylic panel ) sliding shower screen above long bath 580.00

E LIVING ROOM / DINING ROOM ( tiles range from $ 2.5 to $ 3 per sqft )

1 to hack away existing floor finishes and skirting and clear debris off site 1,100.00

2 supply and lay 60 cm x 60 cm Homogenous tiles with skirting 3,600.00

3 supply and install L box 650.00

4 supply and install aluminium casement window for dinnig room 440.00

F BEDROOMS

1 supply labour and tool to varnish existing parquet flooring 750.00

2 to dismantle 3 wardrobes and clear debris off site 300.00

3 to fabricate a full height wardrobe with casement door with laminated finishing and

ABS trimming at main bedroom ( approx 7.5 ft ) 1,680.00

4 to fabricate a full height wardrobe with casement door with laminated finishing and

ABS trimming at bedroom 2 ( approx 6.5 ft ) 1,450.00

5 to fabricate a full height wardrobe with casement door with laminated finishing and

ABS trimming at bedroom 3 ( approx 6.5 ft ) 1,450.00

to seal up ventilation louver above door frame of 3 bedrooms and store room 80.00

4 supply and install aluminium casement window ( silver frame ) with light tinted glass at

3 bedrooms 980.00

G SKIM COAT

1 supply labour , tool and material to provide skim coat to whole house wall and ceiling

except tiling area 2,500.00

H PAINTING WORK

1 supply labour , tool and material to paint oil sealer to skim coat area

2 supply labour and material to paint whole house wall and ceiling including piping 1700.00

, door and door frame ( I C I Pentalite )

I PLUMBING WORK

1 supply and install stainless steel water supply pipe for kitchen and connect inlet and

outlet for kitchen sink and washing machine 700.00

2 to provide hot water point for long bath at master room toilet and shower point at

common toilet 140.00

J ELECTRICAL WORK

1 supply labour , tool and material to provide rewiring work to whole house existing point

including new switch and socket cover and a new Db box 1,800.00

2 labour charge to install all lightings

if additional point required , charges are as followed :

a to provide 13amp single socket $ 40 each

b to provide 13amp double socket $ 55 each

c to provide scv point $ 100 each

d to provide tel point $ 50 each

e to provide lighting point $ 35 each

f labour charge to install light $ 9 each

g to provide 15amp aircon point $ 65 each

h to provide heater point $ 65 each

i to provide door bell point $ 35 each

K OTHERS

1 to remove all cornices F O C

2 HDB permit fee F O C

3 cleaning up upon completion F O C

4 to fabricate shelvng for store room ( 3 tier ) 240.00

TOTAL $44,690

 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

quite cheap. but be careful of hidden cost in the end.

I pointed some weirdness tho' :

Plumbing works doesn't make sense. They hack away the whole toilet floor and wall but then they never include piping replacement cost. Are u expecting to use back the old pipes which most probably will be damaged by the hacking works?

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  

×