  1. 2 hours ago, Reiken said:

    Does James take charge? Cos mine also handled by Edmund... lol.. and yes, just found a major problem..

    He doesn't, you got any issue just call him and liase with him...

    That's what I didn't do till a lot of hiccups come up.

    Some of them are very simple stuff like painting colour, changing of door knobs, coordination of our items to come in, and planning the flow of project and what is needed. One thing that we minded the most is our vinyl not protected throughout and got paints etc. here and there. Its too hard to spot since whole hall & 2 rooms are all vinyl. Really tiring.

    Now we kinda "learnt our lesson".

    James is very prompt in carrying out or rectifying problems and can give good ideas/solutions.


  2. Handover delayed by 2 days at the moment as painting works got mistake and not well communicated. There are paint drips everywhere in parts of our home and not cleaned up.

    Protective flooring also not used and we asked why, E said to help us save cost.

    Its good but shouldnt our opinion be seeked first?

    Many small items like door knobs etc. Etc. not done and even shelving we got from ikea only up today.

    Was wondering why the handover date needed to be postponed but we were still told its today as promised.

    We have already made plans for cleaning today, tomorrow and all items to come in on Monday and E told us our gas, toilet mirrors, shower ledge & painting can only complete on Tues(which we did not take leave for).

    sigh...

    When boss James came he came to check and reminded on the door knobs to be changed and 2 of our kitchen cabinet doors were scratched so he brought back to change.

    James boss to the rescue!

    He also made arrangement for painter to finish the painting works tomorrow before everything delivers on Monday. Seems he is the one who can make everything possible.

    Our sofa, dining table & dining bench have arrived. Mum did the cleaning of whole house while the hub has to go for work after making the drilling arrangements. Thank god!

    image.jpeg


  3. Glad your reno work is up & moving again.

    I guess they move their guys around to meet deadlines and now that they are busy with others, my slowed down relatively a lot.

    From last Fri til today only one master room toilet install plumbing. My kitchen cabinet left without the top from last week and will only be up end of this week.

    Guess cus my is due to complete soon.

    Pls keep the updates coming  =)


  4. 3 hours ago, Json said:

    Stretching the budget abit too much.My contractor told me is cheaper to cut the hood instead of boxed up. Maybe will be cheaper with partial boxed up. 

    But if the hood is cut it will not be as effective? 

    I rem my contractors tellng me something about cutting off but i forgot the reason.

    partial like mine cheaper. But if im staying long i wouldnt mind paying abit more since it will look nicer too... Or if u have a top cabinet, prob solved!


  5. Hubby & me are in love with our house already.

    J&E carpentry work is pretty good.

    So in love with the laminates we chose.

    Only for the sliding wardrobe door, we gonna check with them how come the closing isnt well fitted.

    Our vinyl flooring turned out to be yellowish but cant tell from 1 pieces alone. No choice already chosen.

    Living room with & without lights on :) 

    image.jpeg

     

    Laminates :wub:

    image.jpeg

    Dream kitchen :yeah:image.jpeg

     


  6. 1 hour ago, trcd said:

    Still progressing a little bit each day!

    All plastering done... Cabinets waiting for measurement. Can't see the floor as it is mostly covered by cardboard to protect it.

    IMG_2102.JPG

    The system 3 air con has just gone up! Pics to come this weekend.

    @Honeylee your progress is amazing though. looks like you can move in very soon!

    I guess cus we didnt plaster our walls haha!

    And also our contractor got us to confirm our carpentry pretty early so they can prepare while tiling works are going on.

    Our tentative handover date is 9Jul :)

    i see that you have changed your room entrance. Thats awesome and create more space. Initially we also wanna hack this and that and build walls but our contractor say that that would increase our cost alot and since we are only planning to stay for a good 5yrs and wanna save then do minimal.

    cant wait to see more updates!

     


  7. 6 hours ago, mettaqw said:

    HI Honeylee

    thanks for sharing your experience here. May I know how old is your flat? I read that you did re-wiring, was it for the whole apartment? Mine is about 15 years old, I'm not sure if I need to do re-wiring for the whole flat; which might cost me quite a bit :(

    did your ID recommend to change all the pipes?

    thanks very much.

    Thank u for dropping by my anyhow blog.lol

    our flat is 30+ years old and first owner stayed til now so we changed gas pipes, rewiring and all. Electrical works does cost going by 3k above if not wrong.

    But you can cut cost with this:

    If u go with minimal no. of electrical points & use extension plug instead.

    Ask them to quote u with a basic package based on your needs. If you use less than what they quote u, they should be able to refund you the balance.

    My contractor did not recommend us to change specifically. But we did say we wanna change. I guess if the house is very old it would normally be done since your preferred lighting points will also be different from the previous owner(especially if you are the 2nd owner). Old type electrical points all high on the wall one.

    we are staying for the MOP but still decided to go with rewiring. So if u are looking at long term stay i think its not something you should save on :)

    good luck and do share your reno journey!


  8. ✔️Vinyl & skirting

    ✔️Kitchen & bedroom lightings

    ✔️Carpentry

    We went over after a week from the last progress to check it out & also bring over some taobao lights & things that need to fix up.

    The look of old worn house is finally gone and ous dream place is stating to appear with the box up & first coat of painting(the grey was a wrong grey though) we wanted urban grey not ultra grey. So E said will repaint later.

    Our vinyl looks kinda yellowish and we are finding out why it looks different from the sample.

    Was updated today that carpentry started.

    should be completed by tomorrow.

    really cant wait to see and feel everything tomorrow :rolleyes:

     

    image.jpeg


  9. 7 hours ago, trcd said:

    Are you only unboxing your lightings on the day of installation?

    Found a pendant lamp for the dining area, but have not gotten anything for the living room yet.

    (I actually did - but changed my mind about it so going to get rid of it 8| )

    Actually my lightings came in batches so some are delivered to the current place im staying and some to my new place.I did not unbox those at my new place due to the reno and dust. Those at my current place I have unboxed to repack it into smaller packages.

    You mean you gotten for living room but getting rid? How come?

    If you are interested I can share photos of my lightings taken from the web since I didn't take any pictures.

    For now im rather pleased with some of the lightings I've purchased from taobao(worth it if ship by prime).

    Otherwise I think you can hack some ikea lightings too.

    Also gotten some 4x 0.5m white track lights but after discussion with electrician it can't be of use cause they are too short for my living (I want to go for a brighter look so electrician helping us to get 2 new 2m tracks instead. Also can save on installation cost as they will charge 4x if I install 4x0.5m ones) I also wanna sell off the track lights after house done. Hehe.


  10. 43 minutes ago, Reiken said:

    Lol true... Need go tru the whole process of BSC/HDB again... cos its common toilet tiles... if J&E do, will void warranty... stupid rule... then my estate need to have joint inspection even if they just come up see less than a min... next slot is friday.. very very stupid rule

    Wow that seriously will cause a delay man....

    you can work out with jne to do other stuff firsf so that wont be too much delay? Like electrical or carpentry etc.? Which part of reno are u at now? For mine after tiling works done the rest are pretty fast cus we dun have major works other than tiling & carpentry.

×