Design Services

*Space Planning & Layout Planning.

*Design & Soft Furnishing Consultation.

*Materials & Colour Proposal.

*3D Computerized Perspective Drawings.

*Project Co-ordination & Site Supervision.

*Warranty Period Of 24 Months.

Demolition Works.

Provide protection sheet for flooring during renovation period

$280.00

Provide haulage service & remove debris during renovation period.

$480.00

Chemical & acid cleaning.

$280.00

Masonry Works.

Supply labour & materials to lay selected designer heavy duty homogenous floor

$2,580.00

tiles includes sand / cement screening,chemical adhesive cement, chemical

strengthener bonding membrane ( W.1 ), grouting for tiles gap.

( 600mm x 600mm ) at dining, living & passage way area.

Supply labour & materials to lay HDF laminate flooring c/w skirting at

$730.00

master bedroom area.

Supply labour & materials to lay HDF laminate flooring c/w skirting at

$630.00

common bedroom 2 area.

Supply labour & materials to lay HDF laminate flooring c/w skirting at

$650.00

common bedroom 3 area.

Construct 50mm ht fridge base with complete tiles up.

$150.00

Construct 50mm ht washing machine base with complete tiles up.

$150.00

Construct 50mm ht shower kerb with complete tiles up at master bathroom area.

$120.00

Plumbing Works.

Supply labour & materials to extend / alter cold & hot inlet piping for kitchen

$150.00

sink position.

Provide labour for installation of 02 instant heaters.

$160.00

Provide labour for installation of 02 set toilet fitting & accessories.

Complimentary

Provide labour for installation of 01 kitchen sink.

$80.00

Laying of conceal PVC drainage pipe for 01 kitchen sink.

$50.00

Laying of conceal PVC drainage pipe for 01 washing machine.

$50.00

Carpentry Works.

Design, fabricate & install full ht casement shoes cabinet at foyer area.

$1,120.00

*Perspective drawing provided

Measurement: L 1200mm x D 400mm

Materials: High pressure laminate c/w ABS edging.

Design, fabricate & install full ht T.V. feature wall **** area.

$1,200.00

*Perspective drawing provided

Measurement: L 1800mm x D 100mm

Materials: High pressure laminate.

Design, fabricate & install non - suspended T.V console c/w 01 set of tinted black

$900.00

glass panel **** area.

*Perspective drawing provided

Measurement: L 1800mm x D 450mm

Materials: High pressure laminate c/w ABS edging.

Design, fabricate & install one unit of top & bottom kitchen cabinet.

$3,480.00

Material : High Pressure Laminate with ABS edging

Measurement : Wall Unit------------------------2900mm

Base Unit-----------------------4400mm

01 set aluminium frame frosted glass panel

01 pair of hydraulic system

Stainless steel dish rack

01 pvc cutlery tray

Selected designer's handles

Soft closing hinges

03 set of Soft closing drawer runner

Installation of owner's hood & hob ( Exclude PUB gas piping connection charges )

Supply labour & materials to install solid surface kitchen work-top c/w back splash

$1,350.00

& selected front profile.

Measurement : L 4400mm

Design, fabricate & install full ht built - in oven & pull out wire basket at kitchen

$1,600.00

area.

*Perspective drawing provided

Measurement: L 1000mm x D 600mm

Materials: High pressure laminate c/w ABS edging.

Design, fabricate & install full ht casement wardrobe at master bedroom area.

$3,080.00

*Perspective drawing provided

Measurement: L 3300mm x D 600mm

Materials: High pressure laminate c/w ABS edging.

Ceiling Works.

Supply labour & materials to construct false ceiling effect include internal

$1,280.00

aluminum support ****, dining & passage way area.

( Include curtain pelmet )

Supply labour & materials to construct false ceiling effect include internal

$700.00

aluminum support at master bedroom area.

( Include curtain pelmet )

Painting Works.

Supply labour & provide painting for whole unit's internal walls using NIPPON

$1,350.00

supreme paint (choice of colours) and supply labour & provide painting for whole

unit's ceiling using NIPPON matex paint.

Glass Works.

Supply labour & materials to install 10mm thickness clear tempered glass swing

$580.00

door concept at kitchen entrance area.

Measurement: L 1000mm x H 2100mm

Supply labour & materials to install wall to wall frameless 10mm thickness swing

$480.00

door concept clear tempered glass shower screen at master bathroom area.

Measurement: L 1500mm x H 1800mm

Window Works.

Supply labour & materials to install 01 set of powder coated aluminium

$600.00

sliding windows frame with tinted glass panel at service yard area.

Measurement: L 2400mm

Supply labour & materials to install 01 set of powder coated aluminium

$380.00

sliding windows grill at service yard area.

Measurement: L 2400mm

Total Amount:

$24,640.00

 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

Design Services

*Space Planning & Layout Planning.

*Design & Soft Furnishing Consultation.

*Materials & Colour Proposal.

*3D Computerized Perspective Drawings.

*Project Co-ordination & Site Supervision.

*Warranty Period Of 24 Months.

Demolition Works.

Provide protection sheet for flooring during renovation period

$280.00

Provide haulage service & remove debris during renovation period.

$480.00

Chemical & acid cleaning.

$280.00

Masonry Works.

Supply labour & materials to lay selected designer heavy duty homogenous floor

$2,580.00

tiles includes sand / cement screening,chemical adhesive cement, chemical

strengthener bonding membrane ( W.1 ), grouting for tiles gap.

( 600mm x 600mm ) at dining, living & passage way area.

Supply labour & materials to lay HDF laminate flooring c/w skirting at

$730.00

master bedroom area.

Supply labour & materials to lay HDF laminate flooring c/w skirting at

$630.00

common bedroom 2 area.

Supply labour & materials to lay HDF laminate flooring c/w skirting at

$650.00

common bedroom 3 area.

Construct 50mm ht fridge base with complete tiles up.

$150.00

Construct 50mm ht washing machine base with complete tiles up.

$150.00

Construct 50mm ht shower kerb with complete tiles up at master bathroom area.

$120.00

Plumbing Works.

Supply labour & materials to extend / alter cold & hot inlet piping for kitchen

$150.00

sink position.

Provide labour for installation of 02 instant heaters.

$160.00

Provide labour for installation of 02 set toilet fitting & accessories.

Complimentary

Provide labour for installation of 01 kitchen sink.

$80.00

Laying of conceal PVC drainage pipe for 01 kitchen sink.

$50.00

Laying of conceal PVC drainage pipe for 01 washing machine.

$50.00

Carpentry Works.

Design, fabricate & install full ht casement shoes cabinet at foyer area.

$1,120.00

*Perspective drawing provided

Measurement: L 1200mm x D 400mm

Materials: High pressure laminate c/w ABS edging.

Design, fabricate & install full ht T.V. feature wall **** area.

$1,200.00

*Perspective drawing provided

Measurement: L 1800mm x D 100mm

Materials: High pressure laminate.

Design, fabricate & install non - suspended T.V console c/w 01 set of tinted black

$900.00

glass panel **** area.

*Perspective drawing provided

Measurement: L 1800mm x D 450mm

Materials: High pressure laminate c/w ABS edging.

Design, fabricate & install one unit of top & bottom kitchen cabinet.

$3,480.00

Material : High Pressure Laminate with ABS edging

Measurement : Wall Unit------------------------2900mm

Base Unit-----------------------4400mm

01 set aluminium frame frosted glass panel

01 pair of hydraulic system

Stainless steel dish rack

01 pvc cutlery tray

Selected designer's handles

Soft closing hinges

03 set of Soft closing drawer runner

Installation of owner's hood & hob ( Exclude PUB gas piping connection charges )

Supply labour & materials to install solid surface kitchen work-top c/w back splash

$1,350.00

& selected front profile.

Measurement : L 4400mm

Design, fabricate & install full ht built - in oven & pull out wire basket at kitchen

$1,600.00

area.

*Perspective drawing provided

Measurement: L 1000mm x D 600mm

Materials: High pressure laminate c/w ABS edging.

Design, fabricate & install full ht casement wardrobe at master bedroom area.

$3,080.00

*Perspective drawing provided

Measurement: L 3300mm x D 600mm

Materials: High pressure laminate c/w ABS edging.

Ceiling Works.

Supply labour & materials to construct false ceiling effect include internal

$1,280.00

aluminum support ****, dining & passage way area.

( Include curtain pelmet )

Supply labour & materials to construct false ceiling effect include internal

$700.00

aluminum support at master bedroom area.

( Include curtain pelmet )

Painting Works.

Supply labour & provide painting for whole unit's internal walls using NIPPON

$1,350.00

supreme paint (choice of colours) and supply labour & provide painting for whole

unit's ceiling using NIPPON matex paint.

Glass Works.

Supply labour & materials to install 10mm thickness clear tempered glass swing

$580.00

door concept at kitchen entrance area.

Measurement: L 1000mm x H 2100mm

Supply labour & materials to install wall to wall frameless 10mm thickness swing

$480.00

door concept clear tempered glass shower screen at master bathroom area.

Measurement: L 1500mm x H 1800mm

Window Works.

Supply labour & materials to install 01 set of powder coated aluminium

$600.00

sliding windows frame with tinted glass panel at service yard area.

Measurement: L 2400mm

Supply labour & materials to install 01 set of powder coated aluminium

$380.00

sliding windows grill at service yard area.

Measurement: L 2400mm

Total Amount:

$24,640.00

Hi , can pls pm me..? Thk u vy much.

 

Share this post


Link to post
Share on other sites

Design Services

*Space Planning & Layout Planning.

*Design & Soft Furnishing Consultation.

*Materials & Colour Proposal.

*3D Computerized Perspective Drawings.

*Project Co-ordination & Site Supervision.

*Warranty Period Of 24 Months.

Demolition Works.

Provide protection sheet for flooring during renovation period

$280.00

Provide haulage service & remove debris during renovation period.

$480.00

Chemical & acid cleaning.

$280.00

Masonry Works.

Supply labour & materials to lay selected designer heavy duty homogenous floor

$2,580.00

tiles includes sand / cement screening,chemical adhesive cement, chemical

strengthener bonding membrane ( W.1 ), grouting for tiles gap.

( 600mm x 600mm ) at dining, living & passage way area.

Supply labour & materials to lay HDF laminate flooring c/w skirting at

$730.00

master bedroom area.

Supply labour & materials to lay HDF laminate flooring c/w skirting at

$630.00

common bedroom 2 area.

Supply labour & materials to lay HDF laminate flooring c/w skirting at

$650.00

common bedroom 3 area.

Construct 50mm ht fridge base with complete tiles up.

$150.00

Construct 50mm ht washing machine base with complete tiles up.

$150.00

Construct 50mm ht shower kerb with complete tiles up at master bathroom area.

$120.00

Plumbing Works.

Supply labour & materials to extend / alter cold & hot inlet piping for kitchen

$150.00

sink position.

Provide labour for installation of 02 instant heaters.

$160.00

Provide labour for installation of 02 set toilet fitting & accessories.

Complimentary

Provide labour for installation of 01 kitchen sink.

$80.00

Laying of conceal PVC drainage pipe for 01 kitchen sink.

$50.00

Laying of conceal PVC drainage pipe for 01 washing machine.

$50.00

Carpentry Works.

Design, fabricate & install full ht casement shoes cabinet at foyer area.

$1,120.00

*Perspective drawing provided

Measurement: L 1200mm x D 400mm

Materials: High pressure laminate c/w ABS edging.

Design, fabricate & install full ht T.V. feature wall **** area.

$1,200.00

*Perspective drawing provided

Measurement: L 1800mm x D 100mm

Materials: High pressure laminate.

Design, fabricate & install non - suspended T.V console c/w 01 set of tinted black

$900.00

glass panel **** area.

*Perspective drawing provided

Measurement: L 1800mm x D 450mm

Materials: High pressure laminate c/w ABS edging.

Design, fabricate & install one unit of top & bottom kitchen cabinet.

$3,480.00

Material : High Pressure Laminate with ABS edging

Measurement : Wall Unit------------------------2900mm

Base Unit-----------------------4400mm

01 set aluminium frame frosted glass panel

01 pair of hydraulic system

Stainless steel dish rack

01 pvc cutlery tray

Selected designer's handles

Soft closing hinges

03 set of Soft closing drawer runner

Installation of owner's hood & hob ( Exclude PUB gas piping connection charges )

Supply labour & materials to install solid surface kitchen work-top c/w back splash

$1,350.00

& selected front profile.

Measurement : L 4400mm

Design, fabricate & install full ht built - in oven & pull out wire basket at kitchen

$1,600.00

area.

*Perspective drawing provided

Measurement: L 1000mm x D 600mm

Materials: High pressure laminate c/w ABS edging.

Design, fabricate & install full ht casement wardrobe at master bedroom area.

$3,080.00

*Perspective drawing provided

Measurement: L 3300mm x D 600mm

Materials: High pressure laminate c/w ABS edging.

Ceiling Works.

Supply labour & materials to construct false ceiling effect include internal

$1,280.00

aluminum support ****, dining & passage way area.

( Include curtain pelmet )

Supply labour & materials to construct false ceiling effect include internal

$700.00

aluminum support at master bedroom area.

( Include curtain pelmet )

Painting Works.

Supply labour & provide painting for whole unit's internal walls using NIPPON

$1,350.00

supreme paint (choice of colours) and supply labour & provide painting for whole

unit's ceiling using NIPPON matex paint.

Glass Works.

Supply labour & materials to install 10mm thickness clear tempered glass swing

$580.00

door concept at kitchen entrance area.

Measurement: L 1000mm x H 2100mm

Supply labour & materials to install wall to wall frameless 10mm thickness swing

$480.00

door concept clear tempered glass shower screen at master bathroom area.

Measurement: L 1500mm x H 1800mm

Window Works.

Supply labour & materials to install 01 set of powder coated aluminium

$600.00

sliding windows frame with tinted glass panel at service yard area.

Measurement: L 2400mm

Supply labour & materials to install 01 set of powder coated aluminium

$380.00

sliding windows grill at service yard area.

Measurement: L 2400mm

Total Amount:

$24,640.00

Hi there, can PM me your ID? Thanks!

 

Share this post


Link to post
Share on other sites

Design Services

*Space Planning & Layout Planning.

*Design & Soft Furnishing Consultation.

*Materials & Colour Proposal.

*3D Computerized Perspective Drawings.

*Project Co-ordination & Site Supervision.

*Warranty Period Of 24 Months.

Demolition Works.

Provide protection sheet for flooring during renovation period

$280.00

Provide haulage service & remove debris during renovation period.

$480.00

Chemical & acid cleaning.

$280.00

Masonry Works.

Supply labour & materials to lay selected designer heavy duty homogenous floor

$2,580.00

tiles includes sand / cement screening,chemical adhesive cement, chemical

strengthener bonding membrane ( W.1 ), grouting for tiles gap.

( 600mm x 600mm ) at dining, living & passage way area.

Supply labour & materials to lay HDF laminate flooring c/w skirting at

$730.00

master bedroom area.

Supply labour & materials to lay HDF laminate flooring c/w skirting at

$630.00

common bedroom 2 area.

Supply labour & materials to lay HDF laminate flooring c/w skirting at

$650.00

common bedroom 3 area.

Construct 50mm ht fridge base with complete tiles up.

$150.00

Construct 50mm ht washing machine base with complete tiles up.

$150.00

Construct 50mm ht shower kerb with complete tiles up at master bathroom area.

$120.00

Plumbing Works.

Supply labour & materials to extend / alter cold & hot inlet piping for kitchen

$150.00

sink position.

Provide labour for installation of 02 instant heaters.

$160.00

Provide labour for installation of 02 set toilet fitting & accessories.

Complimentary

Provide labour for installation of 01 kitchen sink.

$80.00

Laying of conceal PVC drainage pipe for 01 kitchen sink.

$50.00

Laying of conceal PVC drainage pipe for 01 washing machine.

$50.00

Carpentry Works.

Design, fabricate & install full ht casement shoes cabinet at foyer area.

$1,120.00

*Perspective drawing provided

Measurement: L 1200mm x D 400mm

Materials: High pressure laminate c/w ABS edging.

Design, fabricate & install full ht T.V. feature wall **** area.

$1,200.00

*Perspective drawing provided

Measurement: L 1800mm x D 100mm

Materials: High pressure laminate.

Design, fabricate & install non - suspended T.V console c/w 01 set of tinted black

$900.00

glass panel **** area.

*Perspective drawing provided

Measurement: L 1800mm x D 450mm

Materials: High pressure laminate c/w ABS edging.

Design, fabricate & install one unit of top & bottom kitchen cabinet.

$3,480.00

Material : High Pressure Laminate with ABS edging

Measurement : Wall Unit------------------------2900mm

Base Unit-----------------------4400mm

01 set aluminium frame frosted glass panel

01 pair of hydraulic system

Stainless steel dish rack

01 pvc cutlery tray

Selected designer's handles

Soft closing hinges

03 set of Soft closing drawer runner

Installation of owner's hood & hob ( Exclude PUB gas piping connection charges )

Supply labour & materials to install solid surface kitchen work-top c/w back splash

$1,350.00

& selected front profile.

Measurement : L 4400mm

Design, fabricate & install full ht built - in oven & pull out wire basket at kitchen

$1,600.00

area.

*Perspective drawing provided

Measurement: L 1000mm x D 600mm

Materials: High pressure laminate c/w ABS edging.

Design, fabricate & install full ht casement wardrobe at master bedroom area.

$3,080.00

*Perspective drawing provided

Measurement: L 3300mm x D 600mm

Materials: High pressure laminate c/w ABS edging.

Ceiling Works.

Supply labour & materials to construct false ceiling effect include internal

$1,280.00

aluminum support ****, dining & passage way area.

( Include curtain pelmet )

Supply labour & materials to construct false ceiling effect include internal

$700.00

aluminum support at master bedroom area.

( Include curtain pelmet )

Painting Works.

Supply labour & provide painting for whole unit's internal walls using NIPPON

$1,350.00

supreme paint (choice of colours) and supply labour & provide painting for whole

unit's ceiling using NIPPON matex paint.

Glass Works.

Supply labour & materials to install 10mm thickness clear tempered glass swing

$580.00

door concept at kitchen entrance area.

Measurement: L 1000mm x H 2100mm

Supply labour & materials to install wall to wall frameless 10mm thickness swing

$480.00

door concept clear tempered glass shower screen at master bathroom area.

Measurement: L 1500mm x H 1800mm

Window Works.

Supply labour & materials to install 01 set of powder coated aluminium

$600.00

sliding windows frame with tinted glass panel at service yard area.

Measurement: L 2400mm

Supply labour & materials to install 01 set of powder coated aluminium

$380.00

sliding windows grill at service yard area.

Measurement: L 2400mm

Total Amount:

$24,640.00

Hi,

How many rooms is yours? Your ID price right?

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  

×