I'm a first time home owner, and was hoping you guys out there can let me know if the quotation by my ID is reasonable. Please let me know what are the important points in a quotation that I should be looking out for, and also is it normal to negotiate the price with IDs. Thank you!

A PROFESSIONAL SERVICE
1 Design consultation & space planning FOC
2 Design proposal & prespective drawings (5 views- $500/-) FOC
3 Selection of colour, material & accessories FOC
4 Site co-ordination & supervision FOC
5 Decoration advice FOC
(FOC under professional service worth total $500)
B MASONRY WORK
1 Supply material & labour to construct motar base at kitchen (14ft L) $420.00
2 Supply material & labour to construct 02 nos. of shower curb at both bathrooms $360.00
*3 Supply material & labour to upload material to house (overlay 2 bathrooms) $800.00
*(Haulage service shall be performed by Town Council appointed contractor)
*4 Supply material & labour to overlay 600mm x 300mm ceramic wall tiles at bath 1 (230sf) $2,530.00
*5 Supply material & labour to overlay 600mm x 300mm ceramic wall tiles at bath 2 (180sf) $1,980.00
*6 Supply material & labour to overlay 300mm x 300mm homogeneous non slipped floor L-Sum $800.00
tile at bath 1
*7 Supply material & labour to overlay 300mm x 300mm homogeneous non slipped floor L-Sum $800.00
tile at bath 2
*(No warranty for overlaying work should issue arise due to underneath layer)
C PLUMBING WORK (Owner Supply Fittings)
1 Supply material & labour to install new stainless steel pipe (exposed) to connect gas heater L-Sum $380.00
hot/ cold water point from service yard to bath 2
2 Supply material & labour to install water inlet/ outlet pipe for basin at bath 1 $80.00
3 Supply material & labour to install water inlet/ outlet pipe for basin at bath 2 $80.00
4 Supply labour to dismantle all bathroom fittings at bath 1 & bath 2 prior to masonry work L-Sum $300.00
5 Supply labour to assemble & install vanity cabinet at bath 1 $100.00
6 Supply labour to install basin & tap at bath 1 $100.00
7 Supply labour to install basin & tap at bath 2 $100.00
8 Supply labour to install bath mixer at bath 1 $80.00
9 Supply labour to install bath mixer at bath 2 $80.00
10 Supply labour to install sitting W.C. at bath 1 $100.00
11 Supply labour to install sitting W.C. at bath 2 $100.00
12 Supply labour to install 02 nos. of spray jet at both bathrooms $80.00
13 Supply labour to install standard 7pcs bathroom accessories for both bathrooms (UP $100/-) FOC
14 Supply labour to install sink & tap at kitchen $100.00
(FOC under plumbing work worth total $100)
D PARQUET WORK
1 Supply & install 3" timber skirting at main bedroom (10ft L) ($250/-) KIV
E PAINTING WORK
1 Supply and paint whole house with original Nippon/ ICI pentalite paint $1,600.00
a 5 colours + 1 ceiling white (matex white)
b paint exposed pipes & door frame for whole house FOC
*c top-up sealer for whole house $300.00
*(Recommended to prevent chalking; minimize hairline cracks; & optimise adhesion)
d paint HS door using chalkboard paint L-Sum $200.00
e includes paint touch up service up to 3 times
F PLASTERCEIL WORK
1 Supply material & labour to construct false ceiling ****/ dining (220sf) $1,100.00
2 Supply material & labour to construct L-Box w/o covelight holder **** room (46ft L) $460.00
3 Supply material & labour to seal 01 no. of ventilation plate for HS $50.00
4 Supply material & labour to construct 01 no. of aircon pelmet **** room $120.00
5 Supply material & labour to construct false beam with wood support at MBR (3ft L) ($180/-) KIV
6 Supply material & labour to construct box-up of aircon trunking (approx. 24ft L) ($360/-) KIV
G GLASS WORK
1 Supply & install 01 set of 10mm tempered clear glass shower screen (fixed panel c/w sliding $700.00
door) at bath 1
2 Supply & install 01 set of L-shaped 10mm tempered clear glass shower screen (fixed panel $850.00
c/w sliding doors) at bath 2
H CUSTOM-MADE FURNITURE
( External: Selected Laminate with width not exceeding 600mm
Internal : Carcass in White PVC Finish )
To supply Labour, Tools And Materials To Install :
LIVING ROOM
1 Design & fabricate suspended TV console (8ft L) $1,040.00
a selected laminate finish
b internal carcass in white PVC finish
c flip-down doors with sandblasted/ black tinted glass doors
d top-up for pocket door configuration ($400/-) Optional item
2 Design & fabricate wall-hung cabinet (8ft L) $1,440.00
a selected laminate finish
b internal carcass in white PVC finish
c cabinet doors with ABS trimmings
d open compartment c/w laminate finish
3 Design & fabricate 04 nos. of laminated casement doors for D.B. box $400.00
a selected laminate finish
4 Design & fabricate suspended full height cabinet (4.5ft L) $1,575.00
a selected laminate finish
b internal carcass in white PVC finish
c cabinet doors with ABS trimmings
d open compartment c/w laminate finish
e clear glass doors for display compartment
5 Design & fabricate movable breakfast table c/w storage (5.5ft L) $990.00
a selected laminate finish
b internal carcass in white PVC finish
c cabinet doors with ABS trimmings
d laminate for exposed back (5.5ft L x 3.5ft H) $230.00
6 Design & fabricate 02 nos. of wall-hung open-concept cabinet (5ft L each) $1,200.00
a selected laminate finish
7 Design & fabricate low height cabinet (8ft L) $1,040.00
a selected laminate finish
b internal carcass in white PVC finish
c cabinet doors/ drawers with ABS trimmings
MAIN BEDROOM
8 Design & fabricate full height sliding doors wardrobe (13ft L) $3,380.00
a selected laminate finish
b internal carcass in white PVC finish
c lockable drawers
d aluminum frame (13ft L) $650.00
e 01 no. of pull-out mirror L-Sum $250.00
9 Supply & install partition wall c/w tic-tac door using MDF board (7.5ft L x 8.5ft H) ($1000/-) KIV
KITCHEN
10 Design & fabricate kitchen cabinet complete with :
a bottom cabinet (14ft L) $1,820.00
b top cabinet (11ft L) $1,430.00
c internal carcass in white PVC finish
d casement doors/ drawers with ABS trimmings
e installation of hob, hood (item supply by owner) FOC
f 01 no of stainless steel dish rack (UP $85/-) FOC
g 01 no. of aluminum frame c/w sandblasted glass door & BLUM Aventos HK system for FOC
dish rack door (UP $450/-)
h top-up for all drawers configuration (14ft L) $420.00
i stainless steel counter top (14ft L) $1,680.00
j stainless steel backing (7ft L x 2.5ft H) $560.00
k Supply & install 03 nos. of BLUM S1 runner track $360.00
l Supply & install 06 nos. of BLUM S3 runner track $900.00
MISCELLANEOUS
11 30 nos. of anti-slam hinges for all cabinet doors (UP $150/-) FOC
12 10 nos. of heavy duty double tracks for all drawers (UP $150/-) FOC
13 top up to color PVC for whole house carpentry work ($2000/-) KIV
(FOC under carpentry work worth total $835) S
I CLEANING WORK
1 Clearing of debris & rubbish throughout renovation period FOC
2 Supply & lay corrugated paper for whole house flooring FOC
3 Provide chemical washing for whole house flooring $180.00
4 Provide general cleaning for whole house flooring upon job completion $150.00
CONTRACT TOTAL: $34,445.00
 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

Hi guys

I'm a first time home owner, and was hoping you guys out there can let me know if the quotation by my ID is reasonable. Please let me know what are the important points in a quotation that I should be looking out for, and also is it normal to negotiate the price with IDs. Thank you!

A PROFESSIONAL SERVICE

1 Design consultation & space planning FOC

2 Design proposal & prespective drawings (5 views- $500/-) FOC

3 Selection of colour, material & accessories FOC

4 Site co-ordination & supervision FOC

5 Decoration advice FOC

(FOC under professional service worth total $500)

B MASONRY WORK

1 Supply material & labour to construct motar base at kitchen (14ft L) $420.00

2 Supply material & labour to construct 02 nos. of shower curb at both bathrooms $360.00

*3 Supply material & labour to upload material to house (overlay 2 bathrooms) $800.00

*(Haulage service shall be performed by Town Council appointed contractor)

*4 Supply material & labour to overlay 600mm x 300mm ceramic wall tiles at bath 1 (230sf) $2,530.00

*5 Supply material & labour to overlay 600mm x 300mm ceramic wall tiles at bath 2 (180sf) $1,980.00

*6 Supply material & labour to overlay 300mm x 300mm homogeneous non slipped floor L-Sum $800.00

tile at bath 1

*7 Supply material & labour to overlay 300mm x 300mm homogeneous non slipped floor L-Sum $800.00

tile at bath 2

*(No warranty for overlaying work should issue arise due to underneath layer)

C PLUMBING WORK (Owner Supply Fittings)

1 Supply material & labour to install new stainless steel pipe (exposed) to connect gas heater L-Sum $380.00

hot/ cold water point from service yard to bath 2

2 Supply material & labour to install water inlet/ outlet pipe for basin at bath 1 $80.00

3 Supply material & labour to install water inlet/ outlet pipe for basin at bath 2 $80.00

4 Supply labour to dismantle all bathroom fittings at bath 1 & bath 2 prior to masonry work L-Sum $300.00

5 Supply labour to assemble & install vanity cabinet at bath 1 $100.00

6 Supply labour to install basin & tap at bath 1 $100.00

7 Supply labour to install basin & tap at bath 2 $100.00

8 Supply labour to install bath mixer at bath 1 $80.00

9 Supply labour to install bath mixer at bath 2 $80.00

10 Supply labour to install sitting W.C. at bath 1 $100.00

11 Supply labour to install sitting W.C. at bath 2 $100.00

12 Supply labour to install 02 nos. of spray jet at both bathrooms $80.00

13 Supply labour to install standard 7pcs bathroom accessories for both bathrooms (UP $100/-) FOC

14 Supply labour to install sink & tap at kitchen $100.00

(FOC under plumbing work worth total $100)

D PARQUET WORK

1 Supply & install 3" timber skirting at main bedroom (10ft L) ($250/-) KIV

E PAINTING WORK

1 Supply and paint whole house with original Nippon/ ICI pentalite paint $1,600.00

a 5 colours + 1 ceiling white (matex white)

b paint exposed pipes & door frame for whole house FOC

*c top-up sealer for whole house $300.00

*(Recommended to prevent chalking; minimize hairline cracks; & optimise adhesion)

d paint HS door using chalkboard paint L-Sum $200.00

e includes paint touch up service up to 3 times

F PLASTERCEIL WORK

1 Supply material & labour to construct false ceiling ****/ dining (220sf) $1,100.00

2 Supply material & labour to construct L-Box w/o covelight holder **** room (46ft L) $460.00

3 Supply material & labour to seal 01 no. of ventilation plate for HS $50.00

4 Supply material & labour to construct 01 no. of aircon pelmet **** room $120.00

5 Supply material & labour to construct false beam with wood support at MBR (3ft L) ($180/-) KIV

6 Supply material & labour to construct box-up of aircon trunking (approx. 24ft L) ($360/-) KIV

G GLASS WORK

1 Supply & install 01 set of 10mm tempered clear glass shower screen (fixed panel c/w sliding $700.00

door) at bath 1

2 Supply & install 01 set of L-shaped 10mm tempered clear glass shower screen (fixed panel $850.00

c/w sliding doors) at bath 2

H CUSTOM-MADE FURNITURE

( External: Selected Laminate with width not exceeding 600mm

Internal : Carcass in White PVC Finish )

To supply Labour, Tools And Materials To Install :

LIVING ROOM

1 Design & fabricate suspended TV console (8ft L) $1,040.00

a selected laminate finish

b internal carcass in white PVC finish

c flip-down doors with sandblasted/ black tinted glass doors

d top-up for pocket door configuration ($400/-) Optional item

2 Design & fabricate wall-hung cabinet (8ft L) $1,440.00

a selected laminate finish

b internal carcass in white PVC finish

c cabinet doors with ABS trimmings

d open compartment c/w laminate finish

3 Design & fabricate 04 nos. of laminated casement doors for D.B. box $400.00

a selected laminate finish

4 Design & fabricate suspended full height cabinet (4.5ft L) $1,575.00

a selected laminate finish

b internal carcass in white PVC finish

c cabinet doors with ABS trimmings

d open compartment c/w laminate finish

e clear glass doors for display compartment

5 Design & fabricate movable breakfast table c/w storage (5.5ft L) $990.00

a selected laminate finish

b internal carcass in white PVC finish

c cabinet doors with ABS trimmings

d laminate for exposed back (5.5ft L x 3.5ft H) $230.00

6 Design & fabricate 02 nos. of wall-hung open-concept cabinet (5ft L each) $1,200.00

a selected laminate finish

7 Design & fabricate low height cabinet (8ft L) $1,040.00

a selected laminate finish

b internal carcass in white PVC finish

c cabinet doors/ drawers with ABS trimmings

MAIN BEDROOM

8 Design & fabricate full height sliding doors wardrobe (13ft L) $3,380.00

a selected laminate finish

b internal carcass in white PVC finish

c lockable drawers

d aluminum frame (13ft L) $650.00

e 01 no. of pull-out mirror L-Sum $250.00

9 Supply & install partition wall c/w tic-tac door using MDF board (7.5ft L x 8.5ft H) ($1000/-) KIV

KITCHEN

10 Design & fabricate kitchen cabinet complete with :

a bottom cabinet (14ft L) $1,820.00

b top cabinet (11ft L) $1,430.00

c internal carcass in white PVC finish

d casement doors/ drawers with ABS trimmings

e installation of hob, hood (item supply by owner) FOC

f 01 no of stainless steel dish rack (UP $85/-) FOC

g 01 no. of aluminum frame c/w sandblasted glass door & BLUM Aventos HK system for FOC

dish rack door (UP $450/-)

h top-up for all drawers configuration (14ft L) $420.00

i stainless steel counter top (14ft L) $1,680.00

j stainless steel backing (7ft L x 2.5ft H) $560.00

k Supply & install 03 nos. of BLUM S1 runner track $360.00

l Supply & install 06 nos. of BLUM S3 runner track $900.00

MISCELLANEOUS

11 30 nos. of anti-slam hinges for all cabinet doors (UP $150/-) FOC

12 10 nos. of heavy duty double tracks for all drawers (UP $150/-) FOC

13 top up to color PVC for whole house carpentry work ($2000/-) KIV

(FOC under carpentry work worth total $835) S

I CLEANING WORK

1 Clearing of debris & rubbish throughout renovation period FOC

2 Supply & lay corrugated paper for whole house flooring FOC

3 Provide chemical washing for whole house flooring $180.00

4 Provide general cleaning for whole house flooring upon job completion $150.00

CONTRACT TOTAL: $34,445.00

Hi it's overpriced already.. A lot of things. Can even show u my quote or u check other company quote. Too much. . The PVC carpentry still need extra 2000. Cabinet also expensive!!! Others come with it. Either u like his design or he's is very special if not I guess u can change another id.

Alan tang

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  


×