Renovation Day 20 (28/05/07)

The wet work still ongoing in the kitchen. Debris has been cleared.

Kitchen:

The tiler still working on the partition wall in the kitchen.

DSCF0118.jpg

We decided on the final location of the mosaic tiles on the kitchen wall.

DSCF0119.jpg

DSCF0120.jpg

DSCF0121.jpg

Master Bedroom

The door frame is up.

DSCF0122.jpg

 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request
Nice new tiles.. I just love to see new tiles. :sport-smiley-004:

You very bold! used green tiles for bathroom. It gives off a modern look. :thumbs up: Great choice. :notti:

I second that! I so envy such nice nice tiles. Mine are H*B given blue tiles! :(

 

Share this post


Link to post
Share on other sites
Wow, ur toilet tiles r very unique... :unsure: ru they exp?

n ur kitchen tiling looks great too.. :notti:

Those toilet tiles are in the package provided by the ID. I didn't top up any thing. For the kitchen wall tiles, bought them from my wife's company. The common bathroom wall tiles and kitchen wall tiles are actually different though they appear similar in the picture.

 

Share this post


Link to post
Share on other sites

Renovation Day 23 (01/05/07)

Kitchen:

The kitchen partition wall is almost up.

DSCF0124.jpg

Plastering work has started. One of the common room plastering work has been completed.

 

Share this post


Link to post
Share on other sites
how do u fix the mosaicinto the wall tiles?

Didn't u see the pic? By masking tape. Just joking. It's done by cutting out portion of the tiles and re-lay the mosaic on to the hole. According to the tiler 'Ah Meng', some special 'kung fu' is needed to cut the tiles without breaking them and he happened to know the 'kung fu'.

 

Share this post


Link to post
Share on other sites

tease me huh!;)!

hehehhehee... this ah meng powerful sia! super curious wif his kungfu, when will he start the 'performance'?

 

Share this post


Link to post
Share on other sites

Renovation Day 25 (28/04/07)

The tiling is completed. Plastering of whole house should be completed by end of the day. Confirmed the location of all plumbing and electrical points. Has also taken delivery of all the sinks, taps, WCs, cooker hoood and hob, lights and other accessories.

Kitchen:

The mosaic tiles is finally mounted on to the wall.

DSCF0132.jpg

DSCF0133.jpg

Common Bathroom:

WC installed.

DSCF0129.jpg

Instant Heater installed.

DSCF0130.jpg

Two-way tap installed.

DSCF0131.jpg

 

Share this post


Link to post
Share on other sites

Renovation Day 27 (05/05/07) (Cont.)

Common Bathroom:

The basin, not sure why the plumber missed the s/s outlet pipe in the same box and use his PVC pipe instead. Already informed ID to rectify.

DSCF0134.jpg

DSCF0164.jpg

Master Bathroom

Basin, same problem with common bathroom. Installed too close to the wall too. Need to rectify.

DSCF0138.jpg

DSCF0139.jpg

Instant heater.

DSCF0140.jpg

 

Share this post


Link to post
Share on other sites

the basin piping that is in white cannot be chge to chrome as the bottle trap ?? it will look much nicer this way...

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  

×