4A HDB, Master Bedroom and corridor floor renovation:
Hacking Works
Supply material and labour to hack existing floor finish at Master Bedroom and corridor $400.00
Provide Sand, Haulage services and debris removal fees $300.00
Masonry Works
Supply and lay 600 mm x 600 mm homogeneous floor tiles at Master Bedroom. $850.00
Supply and lay 600 mm x 600 mm homogeneous floor tiles at Corridor. $200.00
Total: 1750