Hi, Change of plan, is the below quotation is alright? I feel is over quote for the plumbing works. As the toilet bowls, basin, tab need separate purchase. A. Plumbing works Kitchen area A1. Supply labour & material to run inlet S.S pipe for washing machine = $100 A2. Supply labour & material to run outlet PVC pipe for washing = $80 A3. Supply labour to install washing machine tab = $60 Bathroom area A4. Supply labour to dismantle existing WC & basin (2nos) = $300 A5. Supply labour to install WC (2nos) = $240 A6. Supply labour to install basin & tap (2nos) = $160 B. Full wardrobe (pull type) 5.5ft = $1,640 C. Flooring & glass works C1. Supply & apply water proofing (2nos) = $400 C2. Supply labour & material to overlay designer homogeneous floor tiles (2nos) = $1,160 C3. Supply labour & materials to construct shower screen (2nos) = $200 C4. Supply & install 10mm thk temple glass shower screen(2nos)= $1300 D. Miscellaneous works D1. Debris removal = $300 D2. General cleaning of whole unit flooring = $300 Thanks.