Flipwire Design recently completed a renovation for my 3 room resale flat. When I engaged them earlier this year, there weren't many reviews on them. Actually, there still aren't many reviews as of now. So consider this a public service review.
I'm just going to talk about the numbers because opinions are subjective. I was originally given a project schedule of 8 weeks, starting from demolition works day. Demolition works started on 24 April 2017. Keys were handled back to me on 22 September 2017. That's a total of 22 weeks.
22 weeks.