Jump to content
Find Professionals    Deals    Get Quotations   Portfolios

gantan88

Members
  • Content Count

    585
  • Joined

  • Last visited

Everything posted by gantan88

  1. Hi boringgal, who is yr contractor? Name? Thanks :-)
  2. Defects that i have raised, already 3 weeks, they still ask me to give the workers 'somemore time'. I am getting impatient actually. One of the defect - or is this considered as a defect? Install dustbin also will crooked. They left out those 'difficult to reach' corners when plastering. Dunno careless or lazy.
  3. Alright. This is my glass door - finally. Kitchen view: Living Rm View: Box-up cutted to make way for the track, but the glass door installer also go and cut the track to make way for the box-up, dunno what they doing.
  4. Haha.. i will find a time to go Universal Studio. I am taking things slow now. I raised a few points/defects and 2 weeks already still no news. Nevermind. i keep the 5% first....
  5. Pay cash also must see how much.... As i mentioned, this is mentally very draining, got to manage family, work, and this lousy contractor sometimes is just way too much for me to handle...
  6. The last 5% is abt $1000+, definitely worth more than the cabinet that they proposed. I will keep this blog going until my house is fully done up, sofa bought, TV bough, tidy up, take nice shots and post it up. Although now a bit not so active in here coz got to work and stuff like that...
  7. U looking for job? Review on web archi (security) is one of the many things that we do. When u mention CASE, u rekindle the furious flame within me. The AM said even if i go to CASE, he will still win. But i dun think i will want to go to CASE because CASE very inefficient, after months of investigation and mediation, the result/compensation may not even worth me going thru the hassle of logging a case with CASE. I really suck thumb this time. Dunno if i should hold back the 5%. I wan to move on and get on with life...
  8. Update on my kitchen cabinet: I have talked to the boss, apparently they dun seem to be interested and willing to redo the cabinet. But they offer compensation by offering to do up a seperate cabinet in the kitchen for me. I requested for cash compensation (cos' i have lose confidence in them, not willing to ask them do more things) but they have not get back to me yet. I decided to move on, before i get more drained out more because of this kitchen cabinet issue. They will be in my blacklist. Update on my kitchen entrance glass door: Still not done!!!!! They came and take measurement, increase the width of the side partition wall. They also cut the partition (second time already) to see if there is wood support inside for holding the glass slide track). I am worried if the partition wall is still sturdy enuff to hold the weight of the glass - after they cut up the partion wall 2 times (they mend it back using plastering only). Was told today the workers will come to install the glass door, but never come. WTF. As of today, it has been 3 months plus already, including the CNY delays, house not handed over yet. Glass door not installed and they dun see the urgency. Very bad.
  9. I see i see... so u r familiar with web architecture?
  10. Cannot keep it clean and nice. Now quite messy. Maybe it is not messy, but disorganized. Cos accessories not fixed up yet.... Pinkydot... ? Got to look for her blog...
  11. At least you r in charge of your own work. You dun feet the sore of delays. Why wait so long to do up yr cabinet?
  12. Sorry i made a mistake. Anyway, if you look at my kitchen cabinet top now, very messy, cos i temporary place everything on the top. Have not fix up those accessories yet.
  13. Which part of it is messy you mean? The thing on top of my hob is the packaging stuffs. This pic is taken when the hob has not been secured to the ktichen top - simply cut and hole and put it there first. Those moden pull out system drawer etc i opt out. This pic merely show the design of the cabinet but not exactly functional yet because i have not fixed up those things for me to put my sauces, pepper and cooking stuff. I opt out the hood also because it is going to be a white elephant for me. The cabinet is humane, as long as the basics are there - storage space, hob, sink and hood. But given a chance to pay and customise a cabinet, it can be much better....
  14. I am considering to do this. But i have still some other rectification works and the kitchen glass door not done. If i hold back the 5% will they stop all work altogether? Before i make any decision, i will talk to the boss first.
  15. Talking to the AM alone is draining me out, I got so tired. I want my life to go on. They did proper measurement but did not discuss with me on the design. A 3D drawing is only perpsective in nature and they think if i am ok with perspective means i am ok with anything. Worse, now the end product is not even the same as perspective drawing.
  16. Looking at the 3D and the actual thing makes my blood boils. I pay until left the last 5%. The AM talks like he is defending the whole world when i mentioned the option of redoing the cabinet should be open to me. Apparently, tearing down the whole cabinet also affects the walls and the carpentry work backing behind the sink. I got a feeling they are not willing to spend this money.
  17. What do u mean by yr area of work? U r working in this line?
  18. Thanks bro, the links work now. I certainly hope John can give me a more satisfactory explanation and resolution. The AM attitude is like trying to defend the whole world when talking to me.
  19. Ok i get what you mean. It doesn't usually hurt them much. it is just a matter of whether they are willing to do it a not. And it is a huge inconvenience on my side. That's why i said it is a big screw up for my kitchen cabinet. Next time have to be very careful on carpentry work. Lucky i did not do the tv console and shoe rack and wardrobes. I dunno how it will turn out to be.
  20. I am quite drain out talking to the AM. I am going to talk to his boss. This is my last resort. If not i really suck thumb. I dunno what will happen also if i decide to hold back the last payment. Do you know how to insert post link? (My 2 links inside my signature) I can't seem to get it working.
  21. This is a write up on my experience with my Contractor on doing up my kitchen cabinet. Can consider it as a case study for anyone who is considering engaging this company to do up their house. This case study would probably shed some light on how the company runs their business. It would be good to read my general review on the company itself before reading this case study. The link to the general review is at the bottom. Personnel involved: Account Manager (AM), Project Manager (PM) and me. Background: The 3D drawing/perspective drawing of the kitchen cabinet was given to me right at the beginning of the renovation work. The end-product of the kitchen cabinet differs from the perspective drawing. Both drawings are shown at the bottom, at the end of this write-up. ------------------------------------------ Conversation btw the AM and me: Me: Why is the kitchen cabinet not done up according to the perspective drawing? AM: The perspective drawing is a 3 door cabinet (for the bottom part). If we were to do according to the perspective drawing, the door width will be too big, out of proportion. The PM has taken initiative to put in another door since the space now can accommodate 4 doors. If not it will look very ugly. Moreover the perspective drawing does not correctly reflect how the actual end-product will look like in most cases because it is only perspective. Me: Yes, I know. The perspective drawing is done up before the renovation starts when actual site measure is not yet taken. So after all the partition walls are up and site measurement taken, you should at least tell me there is surplus space and we can re-work on the design. Don’t you remember I have a tall-unit item quoted in the quotation? You told me that we will look into that when the available space for the kitchen cabinet is confirmed. With surplus space, I can do other additional things like the tall unit or a wider drawer. You should not just slot in an additional door like that. End up some doors are big some doors are small. AM: Actually to be frank this is how we work, if the customer does not voice out any additional request, we will just do. We cannot have the customer to be involved in every steps of work. It will slow down the progress and make things very difficult. Me: If you did not tell me that there is surplus of space after the actual site measurement, how do I know and made additional request. Morover, the tall-unit is already in the quotation, you knew I had requested for this at the beginning, but subjected to space availability, and can only be confirmed after actual site measurement? This is what you advised me at the beginning right? You said that actually site measurement can only be done once the partition wall is up and plastered. Is this the way you or your company work or is it an industry practice? AM: Actually it is an industry practice. Me: How can this be an industry practice? The kitchen cabinet is a very design focused item in renovation. All designs should go through the customer’s approval before work commence. The cabinet should be designed to suit the customer’s lifestyle, not the other way round. Are you sure this is an industry practice? AM: Everywhere is the same. Like I say, the perspective drawing is only perspective, so after the site measurement, things may change, but the end-product should not be a total different design altogether. In your case, the end-product is not too far off from the perspective drawing right? Me: You already said it is a perspective design. Your designer drew the drawing before any site measurement is taken and the design is simply plucked out from thin air because your designer has no idea of the available space for the kitchen cabinet when she did the drawing. After site measurement is done, the measurement should be given to the designer again to see if any change is needed. But now you are bypassing the designer altogether. The designer is useless, she only draw 3D drawing and nothing else. Instead, you let the carpenter take the lead on the design. Even so, whether it is the carpenter or your designer who design it, the design should come to me first for approval or if time is critical and works are rushing, at least tell me verbally that there are surplus of space now and the design could potentially change. But none of you tell me anything. I am still living in the era of a 3 door cabinet because I thought space cannot accommodate an additional tall-unit. If I had known earlier that there is surplus of space, I will have the option to do the tall-unit. It is already inside the quotation. Is this how you all run your business? I am amazed by how you all do things. This is a serious gap in the work process. AM: You see, actually if you report to CASE, we will still win because this is an industry practice. Our company will not go down because of you – one customer. Anyway, tearing down the whole cabinet now is impossible because we need at least 2 weeks to re-do the cabinet. It is a hassle and cause inconvenience to you, imagine you are not able to use the cabinet for 2 weeks plus? Me: I like to know my options. If inconvenience is not an issue to me, can you tear now the cabinet and re-do. Is cost an issue to you? * At this point, the AM said a lot of things which I not quite remember, but he did not say that the cost of re-doing the cabinet will be borne by him or his company. Instead he emphasize on the hassle and inconvenience I will have, if we choose to re-do the cabinet * AM: …… ok I admit that it is the PM’s fault for not informing you on the surplus of space, so you see, the cabinet is already done and it is looking good, so why not just use it, it is really a waste to tear it down. If you complain that the area on the left is too small to put a microwave, maybe I compensate you by doing up another cabinet for you at the opposite site to put your microwave? Or we can also do other things as compensation or give some discount on other items. Me: Building another cabinet is again taking up more space of my kitchen. If I got a choice, I may want to re-do the cabinet. This choice should remain open to me because we encounter inconvenience in using the cabinet. The stove and the sink is a tad too far apart and makes cooking very troublesome. AM: Most people want a big workspace for their cooking and preparing of ingredients. Now the space you have is quite big, isn’t that good? Me: This is very subjective. Everyone has different way of cooking, you can’t assume everyone cooks the same way. If I got a choice, I do not want any form of compensation. I want a good and USABLE (not only FUNCTIONAL) cabinet. This is the main fundamental reason why people custom made their kitchen cabinet isn’t it? AM: Like I say, tearing down the cabinet is not quite possible because …… * and the AM goes on and on, on the hassle and inconvenience of re-doing the kitchen cabinet * AM: ….. I will come down with John (the AM’s boss) to see how we can help you on this. Meanwhile you think over first ok on the compensation? ………… ----------------------------------------------------- Above is a ‘snapshot’ of the actual conversation over the phone. What is written above is NOT a word-for-word of what has been spoken over the phone but the bulk of the contents are already captured. Sometimes, I realize that the AM also do not know his standpoint. At some point of time he seems to agree that his company has to be responsible (although it is the PM’s fault/carelessness/overlook of this matter) but at some points he is arguing that this is the industry practice and he/they/his company is doing the right thing. And when he mentioned they will surely win even if I report to CASE, I am quite angry and disappointed on how this cabinet thing has turned out to be. My viewpoint is that I have the right to ask them to re-do the kitchen cabinet. They have to be responsible for what the PM has done and left behind (although he has since been dismissed from the company). But from the several conversations that I had with the AM, largely, he doesn’t seems to admit that they are at fault and they are trying their best not to re-do the cabinet (maybe it costs more compared to giving me some monetary discount on other items)? My apology if the above is not written in a clear manner but I certainly hope that it helps any souls out there who is looking for Contractor to do their renovation. Kitchen cabinet is one of the big ticket items inside a renovation project and is very design-focused. Once it is screwed up, you may have to live with it for all you know. As usual, for names of PM and AM, kindly send me private message, I will reveal, Thanks.
  22. Ok, as long as the pipe is not hidden until it is so difficult to clean up if there is a choke. When u say the piping goes around the pipe, it is essentially creating a 'fencing' around the piping? But if there is no wall, how to support the tiles?
  23. Here is the pic. Very close to the wall, dun think can do any skirting there already. How to do re-piping? Have to do hacking work and water-proofing again. Yours is inside the wall? I have it outside because in case there is a choke point somewhere, waste water will start gushing out and i can easily take care of it.
  24. Eh no.. is the washing machine drainage outlet hole pipe, only about 1cm high from the floor, but it is made quite close to the wall. um...
  25. Ossify, until now i still can't figure out how an L-trim looks like and how it enables furnitures to flush to the wall. Do you have a pic of an L-trim? Now i thought of adding skirting to my kitchen flooring but some areas could be block by piping. If an L-trim can save the day, i will consider doing it man...
×