  1. Tough luck... They didn't even bother to reply even after 3 weeks! So I guess that's a big NO
  2. Can try emailing both Singtel and opennet to ask them to waive the $220. I'm trying my luck and still waiting for their reply. Beats not trying at all, right? I managed to get a very early slot and gotten Singtel to waive off all installation and connecting charges so I'm paying $220 at most. I must have appeared very 凶 to them haha
  3. Gotten the LED contact from a follow forumer (is there such a word!?!) and bought 15m worth of LED strip. Going to use 10m of it for cove lights in the living room and remaining 5m for either kitchen cabinet or wardrobe. Haven't decided yet. It's much much much brighter than in the picture. The lights are set to the dimmest and taken using iPhone HDR. Can't wait to see this in action! Also gotten a kitchen tap online that will compliment my 70+cm single-bowl sink. Love online shopping! No need to brave the weather elements to get it
  4. Dropped by to see the progress of the house and I'm pleased! Walked in to see that living tiles are mostly up, kitchen floor and wall tiles almost done, toilet wall tiles done! (I forgot to take pictures of the toilets) Window frames are being installed ( window-man's hair is even longer than mine!) Cabinet base and the low hollow-block wall. Not so keen to use a non-waterproof board so close to water-intensive places. And a nice gesture. We noticed ants crawling in from the refuse chute and notified Wee Kuang and when we came, we saw this: At least no more ants crawling in
  5. Got to adjust my expectations on the speed of the reno.. Looking at so many t-blogs and their speed gave me the impression that it should be speedy SO I just make it a point not to go daily to check on the progress. At least I'd be amazed at the changes between visits. Some updates! Went to Jalan Besar to get the essentials for the toilets and kitchen sink. Walked down almost the whole stretch of Jalan Besar only to be pointed back to Genova for their home-brand kitchen sink. Wanted to get a huge single-bowl sink that is deep enough for baking wares. Bought all from Genova during their clearance sales last week The famous Arino Caprio WC at 40% off (oddly, I didn't take a picture of it) MBR toilet sink at 50% off Common toilet sink Tap for both at 30% off Aluminum mirror cabinet to hide my barang barang Would have worked out to cost us $3200 instead of $2000+ if not for the sale!
  6. Went down to see the progress after a long day of work only to find out that there's a different padlock on the gate and no one's there at 5pm. Propped the wooden door open to peek in and realised subtle changes since yesterday. Wasted trip.
  7. My lastest deliberation: adding cove lights. Thinking of adding cove lights to only 1 side as I love the atmosphere cove lights give but I can't stand the dust. Which side works better? The length above the tv or the opposite side?
  8. Citygas heater during the roadshow in TPY also bought the rainshower set they carried during the roadshow. Figured that if Citygas carried it for their gas heaters roadshow, then it will work with them, right? Also gotten Mitsubishi Heavy Industries system 4 air-con for about $3500. 3x9000btu + 1x18000btu fancoils. Worth it?
  9. Already bought many things even before the renovation started. I'm a classic example of what you call a "kan-cheong spider". EF hood and hob from Gain City Expo sale Samsung washer/dryer from Gain City Expo sale Ariston oven from Mayer KDK ceiling fan (think I bought too big a fan )
  10. Kudos to Wee Kuang and his undying patience to such a fickle person like me. Think I've changed my mind many times over since we signed the contract for the reno (and he must hate renotalk cuz its the source of my fickle-mindedness) Day 3 - Hacking Majority of the things are out except for air-con trunking, some electrical trunking in kitchen and living and the windows. And the puny toilet which looks even smaller when everything is out of the way notice that the opening to the toilet is huge And on my way back, I saw the foam that will be used to raise my dining area to the same height as the living
  11. Initially wanted to sign up with Starhub for their fibre but when HB called, they said we had to liaise with Opennet to do the installation. My house didn't come with the termination point 'cuz the seller ignored all the letters from Opennet. Called Opennet and their "earliest" appointment is in March 2012! The Starhub representative's attitude was rather bad over the phone so HB told them straight that we'd get Singtel instead. Went to Singtel and they managed to expedite the whole Opennet process. Have to sign plan first then Singtel will help you book an appointment with Opennet. Now Opennet will come and install the termination point end November (have to pay $220 for the installation though)
  12. Jia you! My man wasn't very involved in the planning/designing stage so I can empathise with u. As always, renotalk will be there for u
  13. Hacking started on 1 Nov and today Wee Kuang received a phone call from HDB about neighbours complaining about the noise. Any suggestions to pacify them? Hopefully that won't affect the pace of the reno. Targeted hand-over by Wee Kuang to be 24 Dec but my own target is 15 Dec. I don't want to be at home packing on X'mas!
  14. 3Ds! The current 3Ds provided by Wee Kuang is for the structure of the carpentary work, not so much for the colours yet.
  15. Went to choose tiles some time ago. The background is the marble tiles in my parent's house (my current home). No enuff $$$ for marble in my new home. The words on the masking tape over the grey tile is very very misleading. What balcony?
  16. Bedroom 2 Bedroom 3 Kitchen Stuffs from the storeroom Look closely at the picture and you'd spot a sink, w.c. cover, toilet seat, storage water heater and ........ an entire set of car seat for 5 people. The seller left a whole lot of junk for us to clear
  17. Been a long time since I've updated. Didn't even realise how long I was gone till I had to spend 5 minutes to search for my t-blog. Anyhows, I'm back (while it lasts). Lots have happened since the last update. Went for second appointment. Gotten my keys but reno to start 3 months later. Decided against a contractor and selected WaWe Design for my ID. Bought many things. Deliberated over the floor plan for many days, many hours, many ways. Finally decided and paid deposit to secure my $39k reno. Hacking to start tomorrow. Now for pictures After seller moved out Living room MBR
  18. Should be better now? Changed all links to imageshack. More tedious than creating the posts
  19. Thanks for the welcome I'm using ripway actually, since I already had an account. But I think there's something wrong with their server 'cuz it took quite some time for them to load even on my computer
  20. So clever! That day read the news about this old man who got murdered in the park nearby
  21. Didn't go too well We're applying for the flat and grants under fiance/fiancee scheme and didn't know that we had to produce 'evidence' that we're planning to get married. Got to move our ROM date from Nov to Sept so that I had something to give them.
  22. Living, bedroom floor tiles Kitchen wall tiles Kitchen floor tiles Toilet floor tiles Kitchen floor and toilet floor tiles are the same. Not gonna keep the tiles as they are the rough and easy-to-trap-dirt type of tiles. Just look at the toilet tiles Walls for the whole house is done the rock-wall style. added costs to plaster over them
  23. MBR toilet Common toilet The toilets are really small. Initially wanted to place a shower screen in my future toilets but not possible liao. The pipes are in the way and will make the shower space really small.
  24. MBR (from the door) Bedroom 2 (the one beside the MBR) Bedroom 3 Doors Gonna change the whole orientation of the MBR because the toilet door cannot face the bed. The toilet door has been moved closer to the windows by the sellers but now got to shift the door back to the original place. Room door will be moved to the other side of the wall. Bedrooms 2 and 3 appears to be used as storage from what I see. The doors of all bedrooms and store room have this chinese-style carvings. Very ex according to the contractor but it'd go. (yucks)
×