June 7, 201214 yr Dear all,We are thinking of hacking the floor and wall tiles of our common toilet., just wonder how long does it take to do a toilet. My contractor has 9 working days to do so but he kept saying it's not possible to complete. Am so wonder why it takes more than two weeks to complete a toilet? No fancy toilet design, just simple standard of hacking and relay tiles only.Thank you
June 7, 201214 yr Dear all,We are thinking of hacking the floor and wall tiles of our common toilet., just wonder how long does it take to do a toilet. My contractor has 9 working days to do so but he kept saying it's not possible to complete. Am so wonder why it takes more than two weeks to complete a toilet? No fancy toilet design, just simple standard of hacking and relay tiles only.Thank youhacking - 3 dayscement & plastering - 2 dayswaterproofing - 2 dayslaying of floor and wall tiles - 3 daysfitting & fixtures - 2 days3+2+2+3+2 = 12 days = 6 days per week = 2 weeks. Edited June 7, 201214 yr by taichipanda
June 7, 201214 yr Author hacking - 3 dayscement & plastering - 2 dayswaterproofing - 2 dayslaying of floor and wall tiles - 3 daysfitting & fixtures - 2 days3+2+2+3+2 = 12 days = 6 days per week = 2 weeks.I see, thank you for the information. Maybe I should consider overlay instead.
June 7, 201214 yr I see, thank you for the information. Maybe I should consider overlay instead.i am renovating a toilet for 3 weeks, another toilet started work yesterday, it's going to be another nightmare for this old-time client don't have to feel suprise, we are trying to make something different from others.Photos...? later after full completion lah
June 7, 201214 yr Author Still thinking, sinercely might just overlay... No place to stay for three weeks.Will load photo after completion Thanks bros
June 11, 201214 yr Hi!Can share how much is the normal rate for overlay floor + wall tiles?Can also share your contractor contact?Tks!