I haven't been updating the process of my renovation. I have collected my keys from HDB on 7 June 2013 and the renovation offically started on 26 June 2013 One word to describe Darren's team: "PROFESSIONAL" which include the management of tiles, electric, air con, project manager (Roy) and etc. Before they start the project, they will explain the details and the process of the renovation very clearly and provide us with their advice. (I couldn't give the actual date as I only visit on weekend) 1- 30 June 2013: Homegenous tile, fride base and washer base done 2- 6 July 2013: False ceiling, electrical point, air con piping and bath tub installation done