  1. I have a small simple terrace house. Not rebuilding, just intending to upgrade aircons and moving towards induction cooking in the future, and providing for future electric car charging. Currently I have a single phase 60A supply, meter box is within the house compound. Based on all the appliances/induction/heater/aircon that I plan to have, I only need to upgrade to single phase 100A. 3 phase would be overkill. 1. How do I upgrade to single phase 60A to100A? 2. Will I need to relocate the meter box to the gate pillar if upgrade from single phase 60A to 100A? 3. Supposing the meter box does not need to be relocated, will I need to dig up the driveway to lay a new 100A cable? Or can the existing 60A cable in my compound be used and basically SP changes the connection on their end?
×