Blog Entry Date: 3rd November 2017 Friday Click Here to go back to Page 1 - Table of Contents End of 7th week after Key Collection. Carpentry Works - Part 1 / 3
In the previous post, I mentioned that Carpentry Works are going to start on 3rd Nov 2017.
As promised, I just came back onsite and here is my report.
Really wished I could say everything was smooth sailing but I can't. Sigh.
-------------------------------------------------------
So as I'm walking to my apartment, I see all these wooden cabinets outside.
So I think to myself, "Wah....Carpentry Start Liao!!" and started getting excited..... And of course the inside of the place is like a warzone lol!
-------------------------------------------------------
So I bought some drinks for everyone, had abit of a chit-chat with the workers there.
So you know lah, normally, people will start off the conversation like "So how? Everything OK?"
Guess what? Instead of the obligatory "Ya Everything OK", one of the worker VERY HONESTLY,
and in a very dramatic fashion waving his hands around and in a slip of his tongue admitted: "Wah...BIG DISASTER lah..Just now unloading...BANG!!! Thing Fell down" (His Exact Words)
Immediately on the spot stunned like vegetable.
Honestly, I really don't know whether to laugh or cry at that moment.
I regained my composure, then jokingly asked him how bad was it, hoping that I don't sound too stressed. He probably suddenly realized his slip of tongue and quickly replied: "Don't worry I will come back and touch up".
LOL, if you were in my shoes what would you have done?
Sigh...in my heart I thought to myself "Aiyoh....why can't you have told me a lie or something?"
Nope, I didn't lose my temper or anything, since that wouldn't have helped......Sigh...jin suay
Anyway, here are some pictures I took when I was there.
------------------------------------------------------- Workers working on my Kitchen Area.
Gotta admit, I like how its taking shape. That dining table looks nice. This was the "BANG!!" the worker pointed to earlier.
Honestly, I didn't see any big external damage other than the little chipped area that you see circled in RED. Sure, having my cabinet damaged doesn't feel good, but at this point in the renovation, after the shock I had with my Lightings earlier, I kindda, sorta mastered the Art of Zen already lol
As long as the damage isn't too obvious, its guess its alright? Honestly too drained to chase anymore. Luckily its inside the cabinet so I can at the worst case scenario hide it or something. (Of course having it repaired would be better lah!) Here's the side of the Kitchen where i'll have my Induction Cooktop.
Baking Oven will fit in that gaping hole on the left side, and a Microwave will fit into the gaping hole at the right side. This is very ambitious. My Kitchen is already very small. It would be a miracle if I can still somehow fit a Induction Cooktop + Oven + Microwave! Here's the other side of the Kitchen where i'll have my Washing Machine (on the left) and Kitchen Sink (on the right) The Cabinets above the Washing Machine and Kitchen Sink Area Here's the Custom Vanity Mirror Cupboard in the Bathroom My Platform Bed at the Bedroom.
Really liking the mini drawers at the "Steps" area. And now we come to this ACCURSED DB-BOX CABINET.....GRRRR!!!
I feel that this DB-Box has been a CURSE on my renovation so far....
1) Firstly, HDB dunno hire what kind of retarded architect of all the places to put a DB-Box, decide to put the DB-Box right in the Living Room. Grr!
2) Secondly, Having the doors recklessly hacked away only to incur an initial Heart Attack price of $750
3) Now that its negotiated down to $350, guess what problem it has now? The Casement Door looks so LONG in the picture!! The whole idea of Casement Door is to be able to still open it and access the MCB Electrical Box if I have my desk there. Casement Door do so long defeats that purpose right? Is it really so hard to have a Casement Door at the Top Half, and Sliding Door at the Bottom Half
so I can access both areas even if I have a desk there??? Grr!! Ughhh Why can't anything go right with this DB-Box? I have a feeling its cursed. Wadever man, if they can't resolve this, i really can't be bothered anymore. Too drained to chase anymore....Sigh....
Sigh.....so as you can see, first preliminary check on my Carpentry.....isn't 100% perfect. But hey it isn't all bad too. Of course I whatsapped the issues to Jason who again of course advised he will ensure everything is resolved by Handover. (I'm still reeling abit with how Honest that worker admitted to the problem encountered during unloading. Joker really made my day.)
At this point after 7 weeks, I honestly feel abit drained and just want to get it over with.
On the brighter side, most of the other Carpentry works I've seen so far aren't too bad so at least I have that.
Anyway today is just the 1st day of Carpentry, everything is messy so maybe that has also a negative effect psychologically. Do check back tomorrow when I show more progress on what has been done. I'll see you in Part 2 folks~ Click Here for the Next Blog Entry: End of 7th week after Key Collection. Carpentry Works - Part 2 / 3 Click Here to go back to Page 1 - Table of Contents