Hi everyone, below are the quote that my contractor send me, wish to find out from all the expert is there anything wrong with the quotation.
Hacking for kitchen wall and floor tiles
Hacking for both bathroom wall and floor tiles
Dismentle and dispose off of existing kitchen cabinet/sink support
Dismantle and dispose of existing both bathroom pedestal pans
Dismantle and dispose of existing both bathroom wash basins
Dismantle and dispose of both bathroom door / door frames
Masonry works
Supply and lay heavy-duty homogenous flooring for kitchen($3.00psf)
( 5 years warranty )
Supply and lay non-slip homogenous flooring for both bathrooms ($3.00 psf)
( 5 years warranty )
Supply and lay full height designers' wall tiles for kitchen
only ($2.80 sqft) (<330 sqft) ( 5 years warranty)(No wall tiles replace plaster smooth)
Supply and lay full height designers' wall tiles for both bathrooms
($2.80 sqft)(<380 sqft) ( 5 years warranty)
Applications of waterproofing membrance for kitchen and both bathrooms
( 5 years warranty )
Plumbing works
Supply labour and materials to change copper piping for kitchen
and both bathrooms ( cold )
Supply labour & materials to run washing machine inlet/outlet pipe
Supply labour and material to run sink inlet/outlet pipe
Supply labour to install 2 sets pedestal pans and wash basins
Supply labour to install 2 sets instant heater
Supply labour to install 2 sets toilet accessories
Miscellaneous
Supply and install white powdered-coated Aluminium bi-fold door
for both bathrooms
Application of HDB permits
Lay protection sheet for flooring
Chemical washing for whole unit flooring
Total $10988
Kitchen - Supply labour and materials
Supply labour and tiles to construct cement base to recived kitchen cabinet in L-shape. $280.00
Supply labour and tiles to construct cement base for fridge in tiling finish. $100.00
Supply labour and tiles to construct cement base for washing machines in tiling finish. $100.00
Design and fabricate Top and Bottom kitchen cabinet in laminate finish c/w ABS Trimming solid ply doors $1,650.00
include of box-up main sewage pipe. ( 10,600mmL/ 35 ftL ) ( c/w 1 years full warranty ) (Top-up 15Ft length)
Supply and install 2 pcs glass panels FOC
Supply and install stainless steel dish rack FOC
Up-grade of door closer to soft closer.(anti-slam) FOC
Up-grade of drawer runner to heavy-duty "fully retrackable runner track. FOC
Custom made solid surface top for kitchen worktop c/w 50mm fascia include 60mmht backsplash NIL
( 4800mmL/ 16 ftL )
Custom made low-ht wall behind the sink in solid ply wood in laminate finish .
Custom made colour glass wall panelling to kitchen sink cabinet in-between . $520.00
( 3600mmL/ 12 ftL x 700mm ht )
Supply install stainless steel rubbish chute to kitchen $170.00
Supply and paint weathshied paint to kitchen wall. NIL
Supply & install plaster board to box-up main sewage pipe in paint finish . FOC
Supply labour and tool to hack off existing kitchen entrance arch frame mosia tiles and make good the surface . FOC
Up-grade of copper pipe to stainless steel piping. FOC
Supply labour to convert squat to seating bowl type c/w water proofing menbrance . $220.00
Supply labour and emulision painting to whole unit in ICI/nippon paint .(5+1) $1,000.00
Free selection of 3in1 or nippon easy wash paint. FOC
Supply labour and enamel paint all frame,gate and all main sewage pipe. $200.00
Supply labour of haulage for up-loading materail,clearing debris and supply of sand. $450.00
Supply install bronze/silver alum frame 2section sliding window to living hall and bedroom 2 in tinted glass.(40 sqft) $800.00
Supply install bronze/silver alum frame 3panel sliding window to kitchen in tinted glass infill. (32 sqft) $380.00
Supply install bronze/silver alum frame casment window to master bedroom in tinted glass infill. ( 16 sqft) $216.00
Supply install bronze/silver alum grilles to whole unit window.(except bathroom) ( 88 sqft) $620.00
Supply install wrought iron gate to main entrance . $450.00
Supply install solid naytoh timber door to 2 bedroom and store room entrance in lockset and stopper.(3nos) $750.00
Supply & install plaster board to box-up 2 bedroom and store room door above lorver window in paint finish. $100.00
Provisional of supply labour and materail to rewiring of whole unit electrical lighting,power point,tel,scv,water heter and $1,600.00
total damage is 21K
also wanna check out what bank offer the best reno loan?