Everything posted by jthk18
-
2 Storey Coffee Shop
Congrats Kopi... I moved 6 weeks ago... 85% of boxes still remain unpack
-
Jm's Habitat
Never update for a month. Now is already moving in condition. Move some of our stuff on coming Thursday then need to engage a mover to move the balance on coming Sunday. Anyone can recommend a good mover?
-
Any movers to recommend?
kindly pm me jimmy's contact? Thanks in advance.
-
Bad Experience With Mover
Can anyone PM me Richard Contact. thanks in advance
-
2 Storey Coffee Shop
I'm more than happy to take the photo for you kopi, if you don't mind my skill.
-
2 Storey Coffee Shop
Hey kopi... how's your reno going on? mine is 97% done. Can move in anytime lo
-
2 Storey Coffee Shop
Wah... u r half Taiwanese ah?
-
2 Storey Coffee Shop
I nvr been there b4. I heard March is the best time. Will visit next March if i can afford. Totally dry out recently.
-
2 Storey Coffee Shop
I also consider new le. I start few months then stop 1 yr. hahaha...
-
2 Storey Coffee Shop
Simon, u photo kaki also? I like photography also but stop for sometimes. May resume after moving to new place
-
2 Storey Coffee Shop
Welcome back mate. how's your trip?
-
2 Storey Coffee Shop
We same age bro Wish you can complete your reno soon. Enjoy your holiday!
-
Jm's Habitat
According to my Contractor, he is able to complete everything by next week 12 March Master bath tiling works completed New wall @ Study/Bed 4 Gas and Gas Heater installation today , Start wiring today as well Hopefully can see the whole picture next week.
-
Jm's Habitat
10 March Completed 98% of master bath wall tile Common bath completed floor and wall tile. Sunken shower area Kitchen floor tile completed
-
Jm's Habitat
08 March Extend wall to hide sliding door Waterproofing
- Jm's Habitat
-
Jm's Habitat
06 March Received my sanitary ware 95% of common bath wall tile completed
-
Jm's Habitat
05 March A/C installer took 2 days to complete the trunking Bed 1 Bed 1 Bed 3
-
Jm's Habitat
and also some waterproofing and wall tile is up Bath 1 Bath 2 Kitchen Bath 1 Bath 2
-
Jm's Habitat
Let's see what'd happened in one week time... ... 04 March Dismantling old A/C and running new trunking. 1/2" Insulation. In big bundle, can't tell all is 1/2" Upgrade to gauge 22 but they mistakenly installed 23 for me. this one didn't gauge 22 or 23. Maybe is gauge 24
-
Jm's Habitat
03 March Living Bed 1 Kitchen Bath 1 Bath 1
-
Jm's Habitat
02 March - Not much work done, only seal up 2 openning and 1 surface wall tile Bath 1 wall tile Seal up openning
-
Jm's Habitat
01 March - Wall preparation for overlay Kitchen Kitchen Bath 1 Bath 2 Bath 2 - Wall behind waste pipe not covered
-
Jm's Habitat
26 Feb - Hacking + Cleaning Kitchen New openning to Bath 1 Bath 1 Bath 2 Bath 2
-
Jm's Habitat
26 Feb - Hacking + Cleaning Foyer + Entrance Living Bed 1 Bed 3