Jump to content
Find Professionals    Deals    Get Quotations   Portfolios

AWS

Members
  • Content Count

    17
  • Joined

  • Last visited

Community Reputation

1 Neutral

About AWS

  • Rank
    Bronze Member

Previous Fields

  • Gender
    Male

Recent Profile Visitors

The recent visitors block is disabled and is not being shown to other users.

  1. My port clearance agent is able to settle everything after the container arrive singapore port and truck the pallets to reach site and unload everything. Only catch is if one fully maximize the 20ft container to 27 ton, a bigger triple axle truck will be required as normal truck is limited to ferry 24 ton, so extra $50 thereabouts. All the truck comes with build in crane to off load from truck onto site floor. To answer your query, a special crane(unloading device) is required to get the pellets out of the container if you buy slabs, not a normal fork lift. If you buy cut to size tiles, a fork lift is ok to do the job. Slab pallets and cut to size pallets are totally different. The pallets are then placed on the cargo area floor and the truck’s crane is used to load the pallets onto the truck bed and off the truck bed after reaching site. But if one buys slabs from China, then it will be transported to the cutting facility in Singapore. Average cutting service in Singapore is $10 psf thereabouts.
  2. Biggest stone city in the world is in ShuiTou 水头, Xiamen. It’s about 45 minute drive from Xiamen GaoQi International Airport. One can spend weeks just visiting the 水头stone market 市场 alone. Biggest manufacturer of tiles is located in FoShan 佛山, Guangzhou. It is about 60-70 minutes drive from Baiyun international Airport. There are thousands of tiles shop in the tile street. Import container load into Singapore Port is limited to 27 ton. So use a 20 ft container is good enough. A estimate guide for stone of size 600x600x20 is about 500 sqm. Like wise, tile of similiar size but thickness of 10-12mm can load close to 950 sqm. A 20 ft container can load about 15-20 pellets for stone. Shipping usually takes 10-14 days, depends on distance from Singapore. Xiamen is further compared to Guangzhou. Port clearance will cost about $1200-$1300, including transport to site. GST will be charged by government before the container can leave port. If your container arrived too early, storage facility is available and chargeable at $30 per pellet per month limited to 1m cubic size. This a bit of info for people who intend to self import stone/tiles from china.
  3. Snoozee, there are 2 issues with tiles, flatness and 90 degrees angled edge length. A bit hard to put it on writing though. Nowadays, can easily get vetrified edge tiles.
  4. Let me chip in my limited knowledge on tiles and stone differences: 1. For porcelain tiles, the bigger and longish size tiles will end up will slight bent along the edges which can be felt by the foot after laying. Tiles are made made and during the firing process, they are not 100% flat. Marble and granite can be precision cut to achieve flatness to 0.5mm or less, even more demanding tolerance on countertop. Even if the cut to size is not flat, marble can be polished after laying to achieve 100% flatness. Tiles is impossible to be polished. Granite can do very mild polish but still cannot polished off to achieve a 100% flatness after laying due to its hardness. A super heavy polisher is needed to create a down force to wear the top layer and this is an issue for a single man polisher to handle, like for marble. 2. Gaps are required for tiles due to the edges are not 90 degrees to each other. Again because it is man made. Stones can achieve 90 degree angles during cutting. That is why the bigger the tile, the bigger is the gap required, else, the tile layer will have difficulty laying. Imagine the cumulative effect of this small angle difference will propagate a few tilesaway and will end up with a ‘curved alignment’ between 2 ends of a living room. Because of a precision cut of stone, one will notice the gap is only 1-2mm and once polished, the gap lines is hardly noticeable. For tiles, due to the big gap required, the gap lines is forever very noticeable and they will blacken over time and even more noticeable if a white marble tile lookalike was used. So end of the day, there is no perfect solution. Accept the noticeable gap lines or get a nice looking marble floor but with regular maintenance. For tiles, once laid, the gap lines is permanent. For marble, with regular maintenance, it will still look nice and shiny and non noticeable gap lines.
  5. Oh yes. Is it after PP is issued, we have 6 months to make payment for WP? Is it a norm that once PP is obtained, QP will try to delay as long as possible to apply for WP?
  6. I might be wrong but do correct me. You have 6 months to resubmit amendments after submission is approved. But even then, during construction, there is bound to have changed here and there. As long as not major change that affects structure/load bearing, builder is able to do a ‘as built’ drawing submission before TOP.
  7. I think it will be difficult to chip off a bit of the front of the stone wall because the individual stone pieces are relatively big and random in size. Removing the stones will loose your base support for the brick wall above and the brick wall may crack due to lack of base support. I think you will have to redo the whole wall after removing your stone wall plus brick wall. Alternatively, remove the top brick wall, cement plaster the sloping stone wall vertical and join up with a new brick wall. This this case, you have not touch the original position of the stone wall and you have a better chance of getting away if the authories check on your work done
  8. Just to add, if removing the existing attic, you may need to comply to the envelop control requirements by URA and the size of the new attic is under envelop control requirements. Please check with a QP(qualified Person) on your case. https://www.ura.gov.sg/Corporate/Guidelines/Circulars/dc15-02
  9. All replied written directions from the various agencies must be complied with after the fist submission. The agencies involved are: 1. URA (reply by 2 weeks from first submission. I received mine in 3 days) 2. BCA(reply by 2 weeks from first submission. I received mine in 1 week) Written directions from BCA is usually quite a lot as they are very concern with the ajoining neignbor's structure being affected for the whole project. Its can be the abutting wall structure/foundation, depth of foundation of new build up not affecting neighbour's foundation during excavation, beams joining the foundation footings will not affect other structures like RC sewage trench etc 3. PUB(reply by 2 weeks from first submission. I received mine in 1 week) PUB is particularly concern about drainage reserve( if your plot has one). Next of concern is RC sewage trench layout/alignment. 4. LTA(reply by 2 weeks from first submission. I received mine in 1.5 weeks) LTA will be looking out for your kerb design, gradient of ramp access from gate to building structure, gate access facing opposite neighbor's access because now they don't allow change of gate location such that your new gate access will end up directly facing opposite neighbour's gate access, road reserve if there is any in front of your plot, shifting of lamp post due enlarging or relocating gate access. 5. NParks (Reply by 2 weeks from first submission. I received mine in 1 week) NParks will be concern if your plot is in one of the 2 tree conservation areas in singapore and any tree greater than 1 meter girth measured 50cm from the ground. Since Feb 2017, your QP will need to submit a demolition plan to BCA. Additional charges applies, usually $2000. Once the plan is approved, QP will apply for the permit and after obtaining the permit, builder together with owner will need to get signatures from left, right, front and back neighbours for agreement to enter into their premise during the building process to retify anything that was caused damaged by the builder or the portion of work on your new house that can only be done from the neighbour's location.
  10. Just to add, the above is for architect+PE submission. Other fees still required for submission during the construction phase and the TOP/CSC final phase.
  11. Hello everyone, need some information on what are the plan fees required for new erection submission to the various authories. Kindly advice if the below list is not complete. TIA. 1) URA-planning permission S$6,420.002) BCA-structural submission S$2,500.00 (estimated, basedon 4500 SF GFA computation)3) LTA - DC, BP & CSC no charge4) Nparks-DC (internal) S$1,605.00 BP (external) S$2,140.00* pls note that self-declaration of S$107.00 only applicable to comply with downloadable checklist5) NEA-EH/pollution no charge6) PUB-drainage/sanitary/sewer no charge
  12. Just add: https://www.lta.gov.sg/content/ltaweb/en/industry-matters/sale-of-plans-and-information/road-line-plan.html
  13. Hi imzz I just brought a landed at Brockhampton Drive last month. I am in the process of getting started. I had the topographical survey done. You can engage the surveyor yourself or through your architect consultant, or design & build contractor. The price should be in the region of $13xx. I am in the process of searching for an soil & foundation specialist to do a soil test. This should cost about $25xx-$28xx. The soil results will take about a few days from start of drilling. As i know, if your neighbours is within 50-100m who is also doing an rebuild, then you can offer to pay and then share the soil test results, thus saving a bit of money, benefit both parties. You will also need all the structural plans from BCA. If you have not completed your sales (8 weeks from exercise of OTP), then you will need the owner to help you buy the plans, or have his authorization for you or your architect consultant to buy the plans. Search for plans in BCA website is $32 and the plans will be available for download within 5 working days at a cost of $25. You may also want to buy from PUB the SIP(Sewage Infomation Plan), DIP(Drainage Interpretation Plan) and WSP(Water Service Plan). It's good to know where your unit's sewage line runs relative to your landed lot, as anything that is close to your new buildup structural wall will need RC(Reinforcement Contrete) trench protection. My place is only 1 meter depth. So expect the RC works to cost about $15k-20k. The deeper the sewage line, the more expensive its going to get. Getting a first look at the SIP will get you mentally prepared for the extra cost involved. All the PUB plans you can buy yourself and don't need existing owner's authorisation before pirchase online. You may also want to purchase from LTA, the RLP(Road Line Plan) All the above you can ask the consultant to buy on your behalf if you don't want the hassle. There is lots more submissions and hence cost involved for the various government bodies and you must be mentally prepared for the payment required. If you need to discuss, feel free to PM to discuss. But i must say everyday I am still learning and discovering new things on the reubild process.
×