Help! How Long Does It Take For Hdb To Approve Renovation Permit?

Featured Replies

How long does it take HDB to approve renovation permit?

My contractor says it takes 10 days.

We've the key to our new house now, but contractor has not submitted the form to HDB yet.

We're urgent but he's taking his own sweet time.

Is it normal for all contractors to be like tat?

How long does it take HDB to approve renovation permit?

My contractor says it takes 10 days.

We've the key to our new house now, but contractor has not submitted the form to HDB yet.

We're urgent but he's taking his own sweet time.

Is it normal for all contractors to be like tat?

Usually 3 days I think. Mine was applied on a Friday and approved the following Monday. Yours got anything for PE to endorse?

  • Author
Usually 3 days I think. Mine was applied on a Friday and approved the following Monday. Yours got anything for PE to endorse?

U mean engineer?

Hacking of walls require PE to endorse?

U mean engineer?

Hacking of walls require PE to endorse?

Anything that hdb will worry that you will cause damage to their structure, I supposed. Did your id say anything about need special chop? For example, I got a special kerb between kitchen and service balcony that will cost me $600 to remove cos need to get approval. $600 for that chop! Got those metal strips inside. My id say that one take 10 days. Dunno real or not. I left that alone.

mine normal hacking of tiles only. took 3 days

mine normal hacking of tiles only. took 3 days

Depends. Normal hacking of flooring and retiling...3 days

If more complicated like hack wall, tilt door, hack door frame...it is 5-10 days depending on their workload

  • Author
Depends. Normal hacking of flooring and retiling...3 days

If more complicated like hack wall, tilt door, hack door frame...it is 5-10 days depending on their workload

Thks for all your replies.

Yes, we're demolishing the entire wall between the kitchen & the dining

Create an account or sign in to comment

Account

Navigation

Search

Search

Configure browser push notifications

Chrome (Android)
  1. Tap the lock icon next to the address bar.
  2. Tap Permissions → Notifications.
  3. Adjust your preference.
Chrome (Desktop)
  1. Click the padlock icon in the address bar.
  2. Select Site settings.
  3. Find Notifications and adjust your preference.