Looking for good contractors? Click here for your request

Thanks ppl for your advise!

I shall source for another ID and make a comparison then, but sometimes its difficult to tell a real ID from a contractor as there are many contractors around stating that they are a interior design firm.

Hi Storm79

Is not that difficult to tell different between ID & contractor, actually by looking at the price you should know real ID film pricing not much different say about 1-2k different ba, but as for contractor the price is different by 3-5k.

but nevertheless between ID & contractor, i will rather use ID as i don't need to have much headache about handling the contractor, i just need to narrow down to 1 person. My 3cents worth of suggestion. hhehehe.

Maybe you would like to try one of the ID i had known ? as he had done up my house twice and my auntie current house, That i had recommended to her & she is quite happy with the works that they had done. If you needed i can always PM you the address & and his contact number. Hear that he's company had a showroom in Toa Payoh. Let me know if you needed.

cheers

Edited by ideal78
 

Share this post


Link to post
Share on other sites

Hi Storm79

Is not that difficult to tell different between ID & contractor, actually by looking at the price you should know real ID film pricing not much different say about 1-2k different ba, but as for contractor the price is different by 3-5k.

but nevertheless between ID & contractor, i will rather use ID as i don't need to have much headache about handling the contractor, i just need to narrow down to 1 person. My 3cents worth of suggestion. hhehehe.

Maybe you would like to try one of the ID i had known ? as he had done up my house twice and my auntie current house, That i had recommended to her & she is quite happy with the works that they had done. If you needed i can always PM you the address & and his contact number. Hear that he's company had a showroom in Toa Payoh. Let me know if you needed.

cheers

Hi ideal78 for the advise . I will get back to u if I still fail to get a few more quotes from the ID which I have short listed till date .

 

Share this post


Link to post
Share on other sites

Or maybe someone could tell me what's the average market rate of the items from ID not contractor. I.e full height wardrobe per ft run n kitchen cabinet per ft run , feature wall per ft run , The stuff that I listed above . Thanks

 

Share this post


Link to post
Share on other sites

I went to compare my quote with a few in the forum, my capentry is indeed on the ex side but what I feel is that she did not charge me item by item for supplying of labor to install the accessories and piping/ sink/basin and also haulage.

Not so sure if this is justifiable. In a dilemma now..hehE.

Heyz storm,

Actually i feel hor... It also depends on the chemistry between you and the ID too. More chemistry = easier to communicate ma means can convey messages to him/her better also. Cuz i think so far the house owners i met and heard about all asked about site coordination and stuff. Important la... It is always good to have someone there to look after your reno rite? or at least a frequent update on the progress? Many other things count too like service quality, etc.

Oh and of cuz the workmanship. Better quality material and workmanship more ex lo. Apple to apple comparison theory as many would say.

Erm usually electrical works is also quoted de... at least for mine.

Dun dilemma this is part of the reno journey! Have fun dude!

Cheers,

Mike

Wellz my a little bit of advice.

 

Share this post


Link to post
Share on other sites

This is another quote I got from another recommended ID by the forum, what do you all think?

S/N DESCRIPTION T/PRICE

PROFESSIONAL SERVICE

1 Design consultation & space planning FOC

2 Design proposal & prespective drawings FOC

3 Selection of colour, material & accessories FOC

4 Site co-ordination & supervision FOC

5 Decoration advice FOC

6 Apply HDB hacking permit FOC

A HACKING WORKS

1 To demolish existing wall inbetween Dining & Kitchen (6ft L) $600.00

(Subject to HDB approval, not include P.E endorsement (P.E charges from $600 to $800)

2 To demolish existing wall inbetween MBR & Bedroom 2 (6ft L) $600.00

(Subject to HDB approval, not include P.E endorsement (P.E charges from $600 to $800)

3 To dismantle existing wash basin, toilet bowl & shower set at master toilet $300.00

B MASONRY WORKS (Range of tiles up to $3.20) (Additional top up cost for higher range)

1 Supply materials & labour to overlay homogeneous non-slip floor tiles at master toilet $450.00

2 Supply materials & labour to overlay ceramic wall tiles at master toilet (203sf) $1,421.00

3 Supply & construct 2nos. shower kerb,with tiles at master & common toilet $160.00

4 Supply materials & labour to touch up & make good of wall & floor after $450.00

hacking of wall inbetween Living & kitchen

5 Supply materials & labour to touch up & make good of wall & floor after $300.00

hacking of wall inbetween MBR & Bedroom 2

C SHOWER SCREEN / FRAMELESS SANDBLASTED GLASS DOOR (10mm thick tempered glass)

1 Supply & install 10mm thick clear tempered shower screen c/w swing door $550.00

at master toilet

2 Supply & install 10mm thick clear tempered shower screen fix panel $350.00

at common toilet

D PLUMBING WORK (OWNER SUPPLY FITTING)

1 Supply & install water inlet & outlet pipe for sink in kitchen $280.00

2 Supply labour to install kitchen sink $80.00

3 Supply labour to install kitchen tap FOC

4 Supply & install water inlet & outlet pipe for washing machine $60.00

5 Supply labour to install 2 sets toilets accessories in 2 toilets. $60.00

6 Supply labour to install 01 no. of storage tank heater at common toilet $80.00

7 Supply labour to install WC at master toilet $80.00

8 Supply labour to connect & install basin & tap at master toilet $80.00

9 Supply labour to install rain shower set at master toilet $80.00

E PAINTING WORKS-

PREMIUM PACKAGE- ICI WASH & WEAR/ LIGHT & SPACE/ ALL IN 1

1 To paint whole house using ICI / Nippon Paint $1,400.00

a To paint whole house expose copper/pvc pipes FOC

b To paint existing door frame FOC

c 5 + 1 colors

F CEILING WORKS

1 To supply & install false ceiling at Entrance, Living, Dining & Passageway (232sf) $881.60

2 To supply & install L-Box **** (17ft L) $255.00

3 To supply & install cove light holder **** (17ft L) $187.00

4 To supply & install L-Box at Dining (20ft L) $300.00

5 To supply & install cove light holder at Dining (17ft L) $187.00

6 To supply & install false ceiling at MBR (110sf) $418.00

S/N DESCRIPTION T/PRICE

7 To supply & install L-Box at MBR (18ft L) $270.00

8 To supply & install cove light holder at MBR (18ft L) $198.00

G ALUMINIUM WORK

SLIDING WINDOW

1 Supply & install aluminium sliding window at service yard (36sf) $684.00

(Frame colour: Silver) (Glass color: Green)

H CUSTOM-MADE FURNITURE

( External: Selected Laminate with

Internal : Carcass in White PVC Finish )

To supply Labour, Tools And Materials To Install :

ENTRANCE AREA

1 Design & fabricate Simple Full height shoe rack at Entrance (3ft L) OPTION 1 $660.00

Design & fabricate Full height shoe rack c/w display in middle $840.00 OPTION 2

compartment( laminate finish) at Entrance (3ft L)

a Selected Laminate finish

b internal carcass in pvc finish

LIVING AREA

2 Design & fabricate Suspended TV console **** (7ft L) $910.00

a Selected Laminate finish

b internal carcass in white pvc finish

c Aluminium frame glass / laminate door

3 Design & fabricate Full height Feature wall on top of TV console (7ft L) $1,960.00

a Selected Laminate finish

b internal carcass in white pvc finish

c Stainless steel strips / glass / tinted mirror feature

4 Design & fabricate Black tinted mirror c/w wooden backing at dining area (5ft L x 8ft H) $1,000.00

a Selected Laminate finish

b side by side cove lights feature

5 Design & fabricate solid wood pillar with design **** area (4pillars) $960.00

a Selected Laminate finish

b Size per pillar (100mm W x 100mm L)

c glass design

MASTER BEDROOM

6 Design & fabricate Aluminium sliding door Wardrobe at MBR (6ft L) $1,740.00

a Selected Laminate finish

b internal carcass in white pvc finish

c Sliding door opening

d lockable drawer unit

e Adjustable shelves

f Pull out mirror ($180) FOC

g Laminate backing (32sf) $320.00

S/N DESCRIPTION T/PRICE

7 Design & fabricate Low height storage cabinet (10ft L) $1,250.00

a laminate finish

b internal carcass in white pvc finish

c flip up door

8 Design & fabricate Half height Feature wall on top TV console (6ft L) $900.00

a Selected Laminate finish

b top & bottom cove lights feature

c 1no. Of shelve panel (2ft L)($250) FOC

BEDROOM 2

9 Design & fabricate Full Height Casement door Wardrobe (4ft L) $880.00

a Selected Laminate finish

b internal carcass in white pvc finish

c Casement door opening

d lockable drawer unit

MASTER BATHROOM

10 Design & fabricate Suspended Vanity cabinet at master toilet (6ft L) $840.00

a Selected Laminate finish

b internal carcass in white pvc finish

SOLID TOP/ MIRROR

11 Supply & install Solid Surface top above vanity cabinet (6ft L) $510.00

12 Supply & install full length mirror c/w wooden backing for light holder at $720.00

master toilet (6ft L)

COMMON BATHROOM

13 Design & fabricate Suspended Vanity cabinet at common toilet (3ft L) $420.00

a Selected Laminate finish

b internal carcass in white pvc finish

SOLID TOP/ MIRROR

14 Supply & install Solid Surface top above vanity cabinet (3ft L) $255.00

15 Supply & install full length mirror at common toilet (3ft L) $220.00

KITCHEN CABINET

16 Design & fabricate kitchen cabinet complete with :

a Top Hung cabinet 19ft L $1,900.00

b Bottom cabinet (Suspended design) 19ft L $1,900.00

c Bar Counter (Solid surface top) 4ft L $700.00

d Glass Backing 16ft L $1,040.00

e doors in seleted laminate finish and ABS trimmings

f internal carcass in pvc finish

g cutley tray 1 no. FOC

h s/s dish rack 1 no. $160.00

i installation of hob, hood (item supply by owner) 1 no. FOC

j Aluminium frames with sandblasted glass door 1 no. $180.00

k BLUM Anti-slum hinges ($12.00 per hinge) KIV

l BLUM system drawer track ($120 to $180 per track depend on drawer size) KIV

S/N DESCRIPTION T/PRICE

I SOLID SURFACE TOP / GRANITE TOP

1 Supply & install Solid surface top at kitchen approx. (19ft L) OPTION 1 $1,615.00

2 Supply & install Granite top at kitchen approx. (19ft L) $2,470.00 OPTION 2

J CLEANING WORK

1 Haulage & Remove Debris (Pay to HDB's appointed contractor) $550.00

2 Supply Corrugated board to protect existing flooring $380.00

3 Supply labour with acid washing whole house (non-parquet areas) FOC

4 Supply labour for general cleaning before hand over of house FOC

SIN DOLLARS: T/TOTAL : $32,731.60

DISCOUNT : $1,731.60

G/TOTAL : $31,000.00

TERMS & CONDITIONS

Payment Terms

10% of Contract Sum upon Signing & Confirmation

50% of Contract Sum upon Commencement of works

35% of Contract Sum upon Commencement of Carpentry works at Factory

05% of Contract Sum upon Completion

 

Share this post


Link to post
Share on other sites

This is another quote I got from another recommended ID by the forum, what do you all think?

S/N DESCRIPTION T/PRICE

PROFESSIONAL SERVICE

1 Design consultation & space planning FOC

2 Design proposal & prespective drawings FOC

3 Selection of colour, material & accessories FOC

4 Site co-ordination & supervision FOC

5 Decoration advice FOC

6 Apply HDB hacking permit FOC

A HACKING WORKS

1 To demolish existing wall inbetween Dining & Kitchen (6ft L) $600.00

(Subject to HDB approval, not include P.E endorsement (P.E charges from $600 to $800)

2 To demolish existing wall inbetween MBR & Bedroom 2 (6ft L) $600.00

(Subject to HDB approval, not include P.E endorsement (P.E charges from $600 to $800)

3 To dismantle existing wash basin, toilet bowl & shower set at master toilet $300.00

B MASONRY WORKS (Range of tiles up to $3.20) (Additional top up cost for higher range)

1 Supply materials & labour to overlay homogeneous non-slip floor tiles at master toilet $450.00

2 Supply materials & labour to overlay ceramic wall tiles at master toilet (203sf) $1,421.00

3 Supply & construct 2nos. shower kerb,with tiles at master & common toilet $160.00

4 Supply materials & labour to touch up & make good of wall & floor after $450.00

hacking of wall inbetween Living & kitchen

5 Supply materials & labour to touch up & make good of wall & floor after $300.00

hacking of wall inbetween MBR & Bedroom 2

C SHOWER SCREEN / FRAMELESS SANDBLASTED GLASS DOOR (10mm thick tempered glass)

1 Supply & install 10mm thick clear tempered shower screen c/w swing door $550.00

at master toilet

2 Supply & install 10mm thick clear tempered shower screen fix panel $350.00

at common toilet

D PLUMBING WORK (OWNER SUPPLY FITTING)

1 Supply & install water inlet & outlet pipe for sink in kitchen $280.00

2 Supply labour to install kitchen sink $80.00

3 Supply labour to install kitchen tap FOC

4 Supply & install water inlet & outlet pipe for washing machine $60.00

5 Supply labour to install 2 sets toilets accessories in 2 toilets. $60.00

6 Supply labour to install 01 no. of storage tank heater at common toilet $80.00

7 Supply labour to install WC at master toilet $80.00

8 Supply labour to connect & install basin & tap at master toilet $80.00

9 Supply labour to install rain shower set at master toilet $80.00

E PAINTING WORKS-

PREMIUM PACKAGE- ICI WASH & WEAR/ LIGHT & SPACE/ ALL IN 1

1 To paint whole house using ICI / Nippon Paint $1,400.00

a To paint whole house expose copper/pvc pipes FOC

b To paint existing door frame FOC

c 5 + 1 colors

F CEILING WORKS

1 To supply & install false ceiling at Entrance, Living, Dining & Passageway (232sf) $881.60

2 To supply & install L-Box **** (17ft L) $255.00

3 To supply & install cove light holder **** (17ft L) $187.00

4 To supply & install L-Box at Dining (20ft L) $300.00

5 To supply & install cove light holder at Dining (17ft L) $187.00

6 To supply & install false ceiling at MBR (110sf) $418.00

S/N DESCRIPTION T/PRICE

7 To supply & install L-Box at MBR (18ft L) $270.00

8 To supply & install cove light holder at MBR (18ft L) $198.00

G ALUMINIUM WORK

SLIDING WINDOW

1 Supply & install aluminium sliding window at service yard (36sf) $684.00

(Frame colour: Silver) (Glass color: Green)

H CUSTOM-MADE FURNITURE

( External: Selected Laminate with

Internal : Carcass in White PVC Finish )

To supply Labour, Tools And Materials To Install :

ENTRANCE AREA

1 Design & fabricate Simple Full height shoe rack at Entrance (3ft L) OPTION 1 $660.00

Design & fabricate Full height shoe rack c/w display in middle $840.00 OPTION 2

compartment( laminate finish) at Entrance (3ft L)

a Selected Laminate finish

b internal carcass in pvc finish

LIVING AREA

2 Design & fabricate Suspended TV console **** (7ft L) $910.00

a Selected Laminate finish

b internal carcass in white pvc finish

c Aluminium frame glass / laminate door

3 Design & fabricate Full height Feature wall on top of TV console (7ft L) $1,960.00

a Selected Laminate finish

b internal carcass in white pvc finish

c Stainless steel strips / glass / tinted mirror feature

4 Design & fabricate Black tinted mirror c/w wooden backing at dining area (5ft L x 8ft H) $1,000.00

a Selected Laminate finish

b side by side cove lights feature

5 Design & fabricate solid wood pillar with design **** area (4pillars) $960.00

a Selected Laminate finish

b Size per pillar (100mm W x 100mm L)

c glass design

MASTER BEDROOM

6 Design & fabricate Aluminium sliding door Wardrobe at MBR (6ft L) $1,740.00

a Selected Laminate finish

b internal carcass in white pvc finish

c Sliding door opening

d lockable drawer unit

e Adjustable shelves

f Pull out mirror ($180) FOC

g Laminate backing (32sf) $320.00

S/N DESCRIPTION T/PRICE

7 Design & fabricate Low height storage cabinet (10ft L) $1,250.00

a laminate finish

b internal carcass in white pvc finish

c flip up door

8 Design & fabricate Half height Feature wall on top TV console (6ft L) $900.00

a Selected Laminate finish

b top & bottom cove lights feature

c 1no. Of shelve panel (2ft L)($250) FOC

BEDROOM 2

9 Design & fabricate Full Height Casement door Wardrobe (4ft L) $880.00

a Selected Laminate finish

b internal carcass in white pvc finish

c Casement door opening

d lockable drawer unit

MASTER BATHROOM

10 Design & fabricate Suspended Vanity cabinet at master toilet (6ft L) $840.00

a Selected Laminate finish

b internal carcass in white pvc finish

SOLID TOP/ MIRROR

11 Supply & install Solid Surface top above vanity cabinet (6ft L) $510.00

12 Supply & install full length mirror c/w wooden backing for light holder at $720.00

master toilet (6ft L)

COMMON BATHROOM

13 Design & fabricate Suspended Vanity cabinet at common toilet (3ft L) $420.00

a Selected Laminate finish

b internal carcass in white pvc finish

SOLID TOP/ MIRROR

14 Supply & install Solid Surface top above vanity cabinet (3ft L) $255.00

15 Supply & install full length mirror at common toilet (3ft L) $220.00

KITCHEN CABINET

16 Design & fabricate kitchen cabinet complete with :

a Top Hung cabinet 19ft L $1,900.00

b Bottom cabinet (Suspended design) 19ft L $1,900.00

c Bar Counter (Solid surface top) 4ft L $700.00

d Glass Backing 16ft L $1,040.00

e doors in seleted laminate finish and ABS trimmings

f internal carcass in pvc finish

g cutley tray 1 no. FOC

h s/s dish rack 1 no. $160.00

i installation of hob, hood (item supply by owner) 1 no. FOC

j Aluminium frames with sandblasted glass door 1 no. $180.00

k BLUM Anti-slum hinges ($12.00 per hinge) KIV

l BLUM system drawer track ($120 to $180 per track depend on drawer size) KIV

S/N DESCRIPTION T/PRICE

I SOLID SURFACE TOP / GRANITE TOP

1 Supply & install Solid surface top at kitchen approx. (19ft L) OPTION 1 $1,615.00

2 Supply & install Granite top at kitchen approx. (19ft L) $2,470.00 OPTION 2

J CLEANING WORK

1 Haulage & Remove Debris (Pay to HDB's appointed contractor) $550.00

2 Supply Corrugated board to protect existing flooring $380.00

3 Supply labour with acid washing whole house (non-parquet areas) FOC

4 Supply labour for general cleaning before hand over of house FOC

SIN DOLLARS: T/TOTAL : $32,731.60

DISCOUNT : $1,731.60

G/TOTAL : $31,000.00

TERMS & CONDITIONS

Payment Terms

10% of Contract Sum upon Signing & Confirmation

50% of Contract Sum upon Commencement of works

35% of Contract Sum upon Commencement of Carpentry works at Factory

05% of Contract Sum upon Completion

Hi Storm,

Quotation looks reasonable. If you intend to use Solid Surface top check with you id what top he's using.

Another is the payment terms. For mine is usually like this. Gives more assurance for houseowners.

10% before commencement of project

20% upon commencement of wet works

20% upon completion of wet works

20% upon measurement of carpentry works

20% upon completion of carpentry works

10% 7days after completion of project or rectification works if any

Cheers :yamseng: ,

Jaskel

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  

×