Hi guys, i have been emailing IDs and contractors for their quotes on the following. Is this comprehensive enough for a new 4 rm flat with 85 sqm? What else do you think I should include?

Appreciate your assistance.

B. Masonry Works

8 Laying of 600mm x 600mm polished homogeneous floor tiles c/w

skirting ****, dining & store room and bedrooms

10 Construct 50mm cabinet base

11 Construct 50mm washer base

12 Construct 50mm fridge base

14 Construct main entrance kerb

15 Alteration existing main gate

C. Plumbing Works

16 Extension of copper piping to new kitchen sink & washing machine position

17 Labour for installation of storage or instant heater

18 Labour for installation of bathroom accessories

19 Labour for installation of kitchen sink

20 Laying conceal drainage pipe for kitchen sink

21 Laying conceal drainage pipe for washing machine

D. Ceiling Works

22 Construct false ceiling at foyer area

23 Construct false ceiling at bedroom passage way

24 Construct L-box light holder **** area

25 Construct L-box light holder at dining area

26 Construct 2 rolls of L-box light holder at master bedroom

E. Carpentry Works: external in laminate finishes

27 Design & fabricate 20ft kitchen cabinet in ABS trimming door c/w

i design handles & cutlery tray

ii Supply & install stainless steel dish rack

iii Labour to install cooker hood & hob

iv Stainless steel backing at cooker hob

28 Design & fabricate 8'L x 8'Ht feature wall c/w swing door at household shelter

29 Design & fabricate 6'L TV console **** area

30 Design & fabricate 6'L x 6'Ht feature wall above TV console

31 Design & fabricate Study table top for Study room.

F. Miscellaneous / General Services Works

32 Supply & install 10mm tempered glass shower screen at master bathroom

33 Painting of whole unit's wall & ceiling with ICI pentalite emulsion paint

34 Painting of all pipes, doors, door frames & gate with gloss paint

35 Paint or re-vanish of existing main door

36 Laying of floor protection after completion of flooring

37 Chemical washing for whole unit

38 General cleaning upon completion

Others

- 02 x SCV points (1 **** room, 1 at study room)

- 10 x electrical points

- Kitchen Glass door

 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

Yes, I am going to cut away all those feature walls and study table capentry. Hope that helps to trim down my reno costs. Any other things I shld add in? How much is electrical costs that I shld budget?

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  


×