March 12, 201214 yr Author Here con't my update....All according of the reno project...24th Feb... Padlock up...
March 12, 201214 yr Author on 24th Feb contractors all swamp in to take measurement and do markings... They are so pro each doing their own stuff...Later that afternoon cement kerb up for kitchen cabinets....
March 12, 201214 yr Author on 24th Feb contractors all swamp in to take measurement and do markings... They are so pro each doing their own stuff...Later that afternoon cement kerb up for kitchen cabinets....
March 12, 201214 yr Author on 27th Feb painter starting to paint sealer and my 1st coat of medi-fresh Nippon 3in1.....
March 12, 201214 yr Author on 29th Feb... My whole unit completed 2 coat of paint all over.....Nippon Lily White 3106 for living & dinner areasNippon Lilac White 3156 for all bedrooms Edited March 12, 201214 yr by martinsin
March 12, 201214 yr Author On the same day 29th Feb arrival of some of my accessories...Tecno Cooker Hob with safety valveTecno Slimline Hood
March 12, 201214 yr Author Con't......Lightings are here too... Edited March 12, 201214 yr by martinsin
March 12, 201214 yr Author 1st Mar installed some lights to check if everything ok...MBRBedroom 1Bedroom 2Passageway outside common toilet and Foyer using same light...Con't Edited March 12, 201214 yr by martinsin
March 12, 201214 yr Author Contractor also loosen wires for coming TV feature wall and wardrobes....For TV feature wallDinning light point... Edited March 12, 201214 yr by martinsin
March 12, 201214 yr Author Same day toilet accessories were also installed...MBR toiletRainshower cannot install because the existing shower rose length is shorter than rain shower... so if we install at the same position will hit the pipe boxup box on the top.. so gonna shift 1 tile left from the existing location.. sian.. Common toilet
March 12, 201214 yr Author Same day... Both toilet doors make way for my PD door... Edited March 12, 201214 yr by martinsin