1St Em | 2Nd Home | 3Rd Milestone

Featured Replies

Hi, your contractor's works seems to be very professional so far. May I get his contact details from you? Thank you!

  • 2 weeks later...
  • Replies 126
  • Views 51.7k
  • Created
  • Last Reply

Top Posters In This Topic

Most Popular Posts

  • Author

18th May 2015

Its been almost 3 weeks without an update. Sincere apologies for this. However, we are getting along quite ok. Hoping to be able to complete the renovation asap.

Done up Polycarbonate roofing for recess area

F2451838-4C24-4052-9316-68C8314DBC70_zps

Incomplete Kitchen outlook (WIP)

F41F66D3-8B93-47B2-A725-A8B28163BAE8_zps

Current State of living room

25029F8A-C33D-46A3-8707-3429C316F3D9_zps

493E339E-436A-4D72-AC01-8CAA7EA66A82_zps

  • Author

The pictures in the last two posts were taken last week and today we dropped by at night to have a look at how the light fixtures that have been installed.

View of bedroom downstairs before the glass panels are installed.

30D21891-EFC8-4C7F-9BAE-79B5646E78E3_zps

View of corridor, living and balcony

D7F11032-F022-4335-B036-0AAEB50D6570_zps

View of balcony lights from different locations

A9879E06-1F43-476E-B130-B95FC49AE681_zps

9A22DC15-6D8C-426E-9534-820770CD2792_zps

View of New MBR with Lights on

B65ED112-C694-4EFE-8200-A46D7C2E14C1_zps

More installations would be carried out this week. Will hopefully provide updates soon!!

  • Author

Hi, your contractor's works seems to be very professional so far. May I get his contact details from you? Thank you!

Hi ZTZY, thanks. The workmanship is certainly commendable.

The contractor that is working on my project, i believe has been in the business for quite a while but he could still be new in managing larger projects. If you are a very hands on type of customer, then it may work out well but should you want to just sit back and let the contractor handle everything, you must ensure that everything has been agreed upon up front and also there would be notes or agreement terms to fall back on.

In summary, the contractor is a nice person to work with but you do need to ensure that what you have asked and agreed on is delivered. Workmanship is certainly commendable. (sorry for being repetitive)

Sent you the details via PM.

Edited by tiyiz81

Hi, may i have your ID and contractor contacts too pls? Thanks!

  • Author

Hi, may i have your ID and contractor contacts too pls? Thanks!

Hi Elyse18, PM-ed you the contact.

B009C8A5-61BE-4B32-8BDA-3ABB2E42CA75_zps

I LOVE the amount of storage space I see here, sure comes in handy! But I really dislike the internal white PVC look.

Can share where you buy the light colour wood like floor tile & how much is this?

  • Author

I LOVE the amount of storage space I see here, sure comes in handy! But I really dislike the internal white PVC look.

Haha OceanEleven, thanks... I'm pretty sure the wife will have a lot of things to store inside. It was actually the designer's suggestion to do a double sink with full length mirror.

Understood on the PVC look. I'm kind of impartial on that, not that particular. Guess I'm used to seeing it all over hehe.

Thanks for dropping by though hehe.. hope you are enjoying the journey so far...

Can share where you buy the light colour wood like floor tile & how much is this?

Khng, i believe you are referring to the living hall tiles? We got it from White Horse Ceramic, went with my contractor to view before the commencement of the reno. If i don't remember wrongly its $5.50.

tiyiz81 congratulate on your new place! Really jealous that yours is almost done. Can you PM me your contractor contact too. Is he recommended by the ID or did you find him yourself. I like how clean he keep the house and the work done as shown in your picture. I'm in my selection progress and hope to get a responsible one. Thanks in advance..

Jullykhor, thanks for dropping by... no need to get jealous.. it will all be done in due course. We looked for him ourselves. Our designer has their in house contacts as well and they are ok to work with anyone. Yeah his staff do make sure to clean up whenever they can. Also, having a neighbours who keep their surroundings clean helps as well. It will spur the contractor to make sure the location is kept clean.

Have PM-ed you my contractor's contact...

  • Author

25th May 2015

Countdown to Handover......

We are targeting to takeover the unit by end of the week, furnishings should be coming in from 2nd week June onwards.

Mad rush to relocate family into the new home, before we start fasting!!

Seems that things are moving a wee bit faster the last week. "Glass" room, Kitchen as well as staircase will be completed by end of the week.

Installation of the kitchen as well as bathroom fixtures will be done as well..

Excitement for the week but lets show some photos.

Entryway, Shoe Cabinet up!!

F57FF9D3-5773-4707-B4C1-8EAC8CEC9661_zps

Kitchen Fixtures

ED454AE9-061A-41F8-AF85-B718AEDCAB69_zps

Sink installed

6D03590D-77AF-4229-814C-A64D758E639F_zps

Fans for glass room, Haiku and also upstairs bedroom

7600DE81-A6CC-412C-B44A-FF6EBD07140C_zps

983D21E1-C101-4DE2-BE96-F71AD2FB7E1F_zps

725F0A77-0E39-482B-B98B-AD1932EB5701_zps

Edited by tiyiz81

  • Author

Going up the stairs....

Revarnished

1305B909-5193-4A77-ACE6-C09927D63B15_zps

View of New MBR

A250C63B-8543-4683-B615-81430B3D1054_zps

View of the his and hers sink and wall of mirror

CA0A85D0-2794-4AF3-9020-EE8BF6F3FFB0_zps

Common toilet mirror lol!!

0770359F-B719-4B96-97C7-28411036DB50_zps

I really like the look of the subway tiles in the kitchen. This is what I'd want for my kitchen too :)

Can I have your contractor's contact, please?

  • Author

Some photos that were taken when we visited the place yesterday.

'Glass' room being fixed up..

9BA1C892-9797-4C80-96C3-DAF65C6D9BE2_zps

Sinks for Master toilet installed.

7A8F82E0-8808-4276-9B85-537D91D3546E_zps

Staircase repainted and re-stained.

B673ECE3-2AF1-4E80-8980-ABD4F1175983_zps

Dining light installed

4AA9FFF7-60B9-4559-94BA-1AFABA780D91_zps

Dining light against the backdrop of the kitchen entrance

C9313089-29C6-43EF-8567-44D516CF8095_zps

Inside of the shoe cabinet.

AC35B3DF-870E-4965-B78D-0BA395418328_zps

  • Author

I really like the look of the subway tiles in the kitchen. This is what I'd want for my kitchen too :)

Can I have your contractor's contact, please?

Hi Kyooko, thanks...!!

Have sent you the details.

Create an account or sign in to comment

Account

Navigation

Search

Search

Configure browser push notifications

Chrome (Android)
  1. Tap the lock icon next to the address bar.
  2. Tap Permissions → Notifications.
  3. Adjust your preference.
Chrome (Desktop)
  1. Click the padlock icon in the address bar.
  2. Select Site settings.
  3. Find Notifications and adjust your preference.