March 13, 20179 yr Hi Would like to share and records my renovation journey Our new house is a 5-room BTO in AMK and here's our floor plan: Gotten key on Jan 2017 view from service yard View from aircon ledge Edited April 14, 20179 yr by Ken Lam
March 14, 20179 yr Author 34 minutes ago, KFC1189 said: Really fast but nice renovation! Your window views are fantastic! Thanks KFC1189 Not really fast renovation, actually key collected since Jan
March 16, 20179 yr Author Electrical works 7 Feb 17ceiling fans purchased from JBElectrical wiring are concealed for some requested places e.g. fans, lighting, 13A power pointBefore adding lighting point and lighting on/off switchAfter added concealed lighting point and lighting on/off switchBefore adding concealed 13A power point and lighting point After added concealed 13A power point and lighting pt We are pretty happy with the workmanship so far. Plumbing workCold water piping to gas heater and hot water out piping to bathroom Edited March 18, 20179 yr by Ken Lam
March 16, 20179 yr Author Living, master room cove light holder, L-box, curtain pelmet, passageway aircon trunking gas piping box up - Contractor N 14 Feb 17 aircon trucking boxupGas piping boxup Grilles and service yard windows are up Painting - selected Dulux ambience all Edited March 18, 20179 yr by Ken Lam
March 16, 20179 yr Author Carpentry works13 Mar 17 Kitchen! 90% done! Wait for glass backsplash and plumbing works. One of my favorite spot Selected Quartz surface 8015 I love the colours personally.. 16 Mar update on carpentry work like the study desk, very close to our idea Bedroom 2Bedroom 1 Edited March 19, 20179 yr by Ken Lam
March 17, 20179 yr Author Went up to our place yesterday and saw the kitchen clear frameless bi-folding tempered glass door are installed! Unfortunately one of the wall tile crack when they drill the wall to install the door. replaced one of tile and install back the glass door. Edited March 18, 20179 yr by Ken Lam
March 17, 20179 yr Very interesting that you're handling this without an ID or main con =) works look good! Edited March 17, 20179 yr by spooky
March 17, 20179 yr ohhh you doing DIY reno? im tempted to as well, but would it be difficult to coordinate works between different people? or when anything goes wrong they'll start pointing fingers at each other. so far i tried asking individual quotes for carpentry, glass sliding doors, aircon, painting. not any cheaper than what contractors & IDs have quoted me. maybe i just dont have the right contacts.
March 17, 20179 yr Author 11 hours ago, matchalatte said: ohhh you doing DIY reno? im tempted to as well, but would it be difficult to coordinate works between different people? or when anything goes wrong they'll start pointing fingers at each other. so far i tried asking individual quotes for carpentry, glass sliding doors, aircon, painting. not any cheaper than what contractors & IDs have quoted me. maybe i just dont have the right contacts. So far went well for my simple DIY reno. Maybe I'm lucky getting the right contacts. Edited March 18, 20179 yr by Ken Lam
March 18, 20179 yr Hi Kent, Appreciate if can share your electrical and carpentry contacts. Thanks in advance.
March 18, 20179 yr Author electrical & plumbing Jackie 91824672 False ceiling, cove light holder & L box Nick 94502746 Carpenter Ah Gen 90022016 Edited March 18, 20179 yr by Ken Lam
March 18, 20179 yr Hi Ken, I notice your kitchen bi-folding glass door blocks the kitchen switches when it is open. So if you want to turn on the kitchen light, first you have to close the kitchen door, then turn on the switch and then reopen the kitchen door. This is not ideal in my opinion. You may want to relocate the switches to the other side of the wall.