Will be sharing our purchases over the next few posts (no TB purchase yet though).

Bought quite a lot of stuff in our one week marathon back in SG last week. Rush here rush there and now I'm down with the flu :~ But for our dream home, it's still worth it :lol:

For the past week, we bought our lights, toilet accessories, toilet sink & tap, kitchen sink & mixer and ceiling fans. Came out of every shop at least $1k poorer :jawdrop: Even though already budgeted for the purchases, still feel very :o by the end of the week!

If you guys have the time and know how to purchase from TB, it seems like a really worthwhile place to get your loots. I will do that for my house deco items, probably for dining table and coffee / side table and things like clocks etc :wub:

 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

Renovation Day 6 - 24 April

Air con trunking and electrical works were done up.

Lighting points in living room.

photo1-9.jpg

Lighting + air con trunking in living room.

photo2-10.jpg

Air con trunking in MBR.

photo-3.jpg

Other bedrooms.

photo5-7.jpg

photo4-9.jpg

 

Share this post


Link to post
Share on other sites

Nope~~ but the hse is in living state alr ... less those small appliances n etc stuff to buy ... haha been cleaning n cleaning n cleaning :/ ... Didn't c u ard the neighbourhood leh!

Haha, after the cleaning then can concentrate on shifting in liao, must be an amazing feeling!

I'm dreading the cleaning and cleaning stage.. But maybe will feel different coz its our own home! :wub:

I went to my unit quite a few days last week, but we only went to our own block. Didn't see any neighbour at all.. Think still collecting keys. Saw on FB page the key collection date is all the way till mid May :wacko:

 

Share this post


Link to post
Share on other sites

Nope~~ but the hse is in living state alr ... less those small appliances n etc stuff to buy ... haha been cleaning n cleaning n cleaning :/ ... Didn't c u ard the neighbourhood leh!

Thank you neighbour!

Have you officially moved in?

 

Share this post


Link to post
Share on other sites

Renovation Day 4 - 22 April (Part 2)

One last pic - cardboard all laid in living room.

photo-2.jpg

Next up:

False ceiling, air con trunking and electrical points will be done over the next few days.

Once those done, painting work will begin.

At the same time, patiently waiting for our carpentry detailed drawing to be out :sport-smiley-018:

 

Share this post


Link to post
Share on other sites

Renovation Day 4 - 22 April

Paid the next 30% of our reno fees yesterday to start all the work.

Reno progressing well. Kitchen / fridge / washing machine bases all done up yesterday!

Fridge and washing machine base tiles are slightly lighter than the ones by HDB. We are okay with it since they are hidden anyway. It's just funny why the HDB contractors don't buy more so we can use the same tiles. Keep asking all the IDs to go to their supplier, and supplier also don't have anymore stock -.-"

photo4-8.jpg

photo5-6.jpg

photo3-9.jpg

Toilet kerbs done up nicely too :lol:

photo2-9.jpg

The backing of our toilet bowl is also extended upwards by another 2 inches, as we bought a taller WC.

photo1-8.jpg

 

Share this post


Link to post
Share on other sites

Hi Karen,

do you mind sharing your detailed quote and ID to shangesonyap@gmail.com thanks in advance :help::good:

HI Jia Wen,

Can pm your FSM, his rate and your ID.

Thank you! :)

PM-ed :)

 

Share this post


Link to post
Share on other sites

Renovation Day 3 - 21 April

Yesterday was the day when renovation started full force. Putting pics to let it do the talking.

We bought 4 cartons of mineral water for the workers (supposed to last them through the entire 6 weeks of renovation).

photo1-7.jpg

Equipments all stacked on top of cardboards to start the base for my kitchen cabinets, fridge and washing machine.

Can also see the uncle in the kitchen opening drawing out the dimensions of the base on the floor.

photo2-8.jpg

The cement (i think) placed at the correct places!

photo4-7.jpg

photo5-5.jpg

This was all we saw so far today. Heading down again tomorrow to pass our ID some stuff. Hopefully there's more photos to update!

I think i'm getting separation anxiety from the renovation :~

Was cracking my brains this morning trying to run through anything I may have forgotten or missed out. Hubby was totally calm and just standing around waiting for me to finish thinking :bangwall: Guess he really TOTALLY left all decisions to me for this renovation, just as I wished for :lol:

But anyway my ID sensed my gan cheong-ness i think, and kept reassuring me that if we forget anything, he is just a whatsapp or Skype call away. He will also take photos for us whenever there are updates to the renovation :wub:

I'm particularly thankful that he offered to schedule all our deliveries and check and receive them on our behalf. It is practically impossible for us to do so and may be really tiring for my mum to run up and down to do it. Especially since delivery timing are always not fixed and span over a few hours. By doing so, he already told us he takes the responsibility if things get stolen or broken. So he will ensure our house is locked well everyday :sport-smiley-018:

So far, all raves and no rants for my ID :dancingqueen:

 

Share this post


Link to post
Share on other sites

Renovation Day 1 - 19 April

Knocking of my MBR toilet vanity + WC on the auspicious start renovation day

Hubby & mum say v sayang... but... I really don't like.... so CHANGE!

photo3-8.jpg

Okay that was the only thing done that day as my ID couldn't coordinate his contractors + gather the raw materials since the day before was a PH.

Remember to shout HUAT AH loud loud when knocking the right spot at the auspicious time.

It's also encouraged to give a red packet to the person knocking the spot. Kind of like symbolising luck for the renovation.

Edited by guojiawen
 

Share this post


Link to post
Share on other sites

Updates on Defects



Summary of post #394 + #395



1. Two scratches on bomb shelter door


2. Gaps found on the rubber of one window (Not sealed properly)


3. Plastering not done properly on wall


4. Corner skirting was slanted


5. Bottom of skirting was filled with white cement instead of silicon / top silicon not filled properly


6. Broken tile in common toilet beside the WC


7. Holes in wall tiles grout lines in toilet + kitchen


8. Uneven tiles + grout lines that are too deep



Defects reported to BSC on 15th April + 1 additional defect reported to BSC on 19 April.



All defects rectified as of 21 April :good:


 

Share this post


Link to post
Share on other sites

Noted with thanks. By chance, I just saw received a junk mail in my mailbox that caught my attention. Check out their website and read "About Us".

http://www.fengshuiorganizers.com/

Checked it out, but doesn't say much? :)

Its just a site to buy things that help to organise our house to make it less cluttered? Or did I miss anything?

 

Share this post


Link to post
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Sign in to follow this  

×